DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA BIAYA No. URAIAN KO HP KAP. HARGA SEWA KET. DE ALAT ALAT/JAM (di luar PPN) 1 ASPHALT MIXING PLANT E01 294.0 60.0 T/Jam 2,500,000,000 7,164,668.19 2 ASPHALT FINISHER E02 72.4 10.0 Ton 1,200,000,000 666,483.98 3 ASPHALT SPRAYER E03 4.0 850.0 Liter 121,000,000 72,070.59 4 BULLDOZER 100-150 HP E04 155.0 - - 700,000,000 524,129.78 5 COMPRESSOR 4000-6500 L\M E05 60.0 5,000.0 5,000.00 110,000,000 172,094.05 6 CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 175,500,000 174,253.93 7 CRANE 10-15 TON E07 138.0 15.0 Ton 800,000,000 517,659.66 8 DUMP TRUCK 3.5 TON E08 100.0 5.0 Ton 200,000,000 276,760.34 9 DUMP TRUCK 10 TON E09 200.0 8.0 Ton 300,000,000 504,056.23 10 EXCAVATOR 80-140 HP E10 133.0 0.9 M3 800,000,000 507,669.66 11 FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 330,000,000 492,325.00 12 GENERATOR SET E12 180.0 135.0 KVA 207,000,000 438,525.06 13 MOTOR GRADER >100 HP E13 135.0 10,800.0 10,800.00 900,000,000 539,161.55 14 TRACK LOADER 75-100 HP E14 70.0 0.8 M3 542,000,000 310,856.28 15 WHEEL LOADER 1.0-1.6 M3 E15 96.0 1.5 M3 900,000,000 461,239.55 16 THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 350,000,000 228,094.17 17 TANDEM ROLLER 6-8 T. E17 82.0 8.1 Ton 750,000,000 392,023.72 18 TIRE ROLLER 8-10 T. E18 100.5 9.0 Ton 700,000,000 415,238.78 19 VIBRATORY ROLLER 5-8 T. E19 82.0 7.1 Ton 600,000,000 350,779.89 20 CONCRETE VIBRATOR E20 5.5 25.0 25.00 4,000,000 37,984.27 21 STONE CRUSHER E21 220.0 50.0 T/Jam 1,500,000,000 882,754.30 22 WATER PUMP 70-100 mm E22 6.0 - - 5,000,000 35,642.58 23 WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 90,000,000 246,514.87 24 PEDESTRIAN ROLLER E24 8.8 835.00 Ton 150,000,000 90,131.22 25 TAMPER E25 4.7 121.00 Ton 17,000,000 44,094.77 26 JACK HAMMER E26 0.0 1,330.00 1,330.00 35,000,000 31,592.13 27 FULVI MIXER E27 345.0 2,005.00 2,005.00 900,000,000 1,429,949.92 28 CONCRETE PUMP E28 100.0 8.00 M3 112,500,000 250,970.57 29 TRAILER 20 TON E29 175.0 20.00 Ton 700,000,000 553,319.90 30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 875,000,000 312,507.58 31 CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 850,000,000 492,355.89 32 WELDING SET E32 40.0 250.0 Amp 17,500,000 106,700.35 33 BORE PILE MACHINE E33 150.0 2,000.0 Meter 2,000,000,000 840,815.21 34 ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 15,000,000 36,431.75 35 TRONTON E35 150.0 15.0 Ton 604,995,000 613,826.64 36 COLD MILLING E36 248.0 1,000.0 m 4,945,000,000 1,894,719.02 37 ROCK DRILL BREAKER E37 3.0 - - 900,000,000 352,305.94 38 COLD RECYCLER E38 900.0 2.2 M 19,500,000,000 7,199,441.32 39 HOT RECYCLER E39 400.0 3.0 M 29,250,000,000 8,881,290.27 40 AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 395,000,000 567,905.80 41 ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 395,000,000 377,922.18 42 SLIP FORM PAVER E42 105.0 2.5 M 1,337,142,857 596,420.04 43 CONCRETE PAN MIXER E43 134.0 600.0 Liter 1,000,000,000 708,497.33 44 CONCRETE BREAKER E44 290.0 20.0 m3/jam 900,000,000 866,426.41 45 ASPAHLT TANKER E45 190.0 4,000.0 liter 500,000,000 572,975.23 46 CEMENT TANKER E46 190.0 4,000.0 liter 500,000,000 531,375.23 47 CONDRETE MIXER (350) E47 20.0 350.0 liter 35,000,000 76,472.32 48 VIBRATING RAMMER E48 4.2 80.0 KG 20,000,000 44,729.05 49 TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 750,000,000 667,747.72 50 BORE PILE MACHINE E50 125.0 60.0 CM 1,170,000,000 726,465.84 51 CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 900,000,000 669,031.55 52 BLENDING EQUIPMENT E52 50.0 30.0 Ton 500,000,000 256,292.19 53 ASPHALT LIQUID MIXER E34a 40.0 20,000.0 Liter 15,000,000 106,361.75 Jakarta , 27 Maret 2016 PENAWAR

Upload: holiq-hidayat

Post on 13-Jul-2016

12 views

Category:

Documents


4 download

DESCRIPTION

JJB L

TRANSCRIPT

DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA

No. URAIAN KO HP KAP. HARGA SEWA KET.DE ALAT ALAT/JAM

(di luar PPN)

1 ASPHALT MIXING PLANT E01 294.0 60.0 T/Jam 2,500,000,000 7,164,668.19

2 ASPHALT FINISHER E02 72.4 10.0 Ton 1,200,000,000 666,483.98

3 ASPHALT SPRAYER E03 4.0 850.0 Liter 121,000,000 72,070.59

4 BULLDOZER 100-150 HP E04 155.0 - - 700,000,000 524,129.78

5 COMPRESSOR 4000-6500 L\M E05 60.0 5,000.0 5,000.00 110,000,000 172,094.05

6 CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 175,500,000 174,253.93

7 CRANE 10-15 TON E07 138.0 15.0 Ton 800,000,000 517,659.66

8 DUMP TRUCK 3.5 TON E08 100.0 5.0 Ton 200,000,000 276,760.34

9 DUMP TRUCK 10 TON E09 200.0 8.0 Ton 300,000,000 504,056.23

10 EXCAVATOR 80-140 HP E10 133.0 0.9 M3 800,000,000 507,669.66

11 FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 330,000,000 492,325.00

12 GENERATOR SET E12 180.0 135.0 KVA 207,000,000 438,525.06

13 MOTOR GRADER >100 HP E13 135.0 10,800.0 10,800.00 900,000,000 539,161.55

14 TRACK LOADER 75-100 HP E14 70.0 0.8 M3 542,000,000 310,856.28

15 WHEEL LOADER 1.0-1.6 M3 E15 96.0 1.5 M3 900,000,000 461,239.55

16 THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 350,000,000 228,094.17

17 TANDEM ROLLER 6-8 T. E17 82.0 8.1 Ton 750,000,000 392,023.72

18 TIRE ROLLER 8-10 T. E18 100.5 9.0 Ton 700,000,000 415,238.78

19 VIBRATORY ROLLER 5-8 T. E19 82.0 7.1 Ton 600,000,000 350,779.89

20 CONCRETE VIBRATOR E20 5.5 25.0 25.00 4,000,000 37,984.27

21 STONE CRUSHER E21 220.0 50.0 T/Jam 1,500,000,000 882,754.30

22 WATER PUMP 70-100 mm E22 6.0 - - 5,000,000 35,642.58

23 WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 90,000,000 246,514.87

24 PEDESTRIAN ROLLER E24 8.8 835.00 Ton 150,000,000 90,131.22

25 TAMPER E25 4.7 121.00 Ton 17,000,000 44,094.77

26 JACK HAMMER E26 0.0 1,330.00 1,330.00 35,000,000 31,592.13

27 FULVI MIXER E27 345.0 2,005.00 2,005.00 900,000,000 1,429,949.92

28 CONCRETE PUMP E28 100.0 8.00 M3 112,500,000 250,970.57

29 TRAILER 20 TON E29 175.0 20.00 Ton 700,000,000 553,319.90

30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 875,000,000 312,507.58

31 CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 850,000,000 492,355.89

32 WELDING SET E32 40.0 250.0 Amp 17,500,000 106,700.35

33 BORE PILE MACHINE E33 150.0 2,000.0 Meter 2,000,000,000 840,815.21

34 ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 15,000,000 36,431.75

35 TRONTON E35 150.0 15.0 Ton 604,995,000 613,826.64

36 COLD MILLING E36 248.0 1,000.0 m 4,945,000,000 1,894,719.02

37 ROCK DRILL BREAKER E37 3.0 - - 900,000,000 352,305.94

38 COLD RECYCLER E38 900.0 2.2 M 19,500,000,000 7,199,441.32

39 HOT RECYCLER E39 400.0 3.0 M 29,250,000,000 8,881,290.27

40 AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 395,000,000 567,905.80

41 ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 395,000,000 377,922.18

42 SLIP FORM PAVER E42 105.0 2.5 M 1,337,142,857 596,420.04

43 CONCRETE PAN MIXER E43 134.0 600.0 Liter 1,000,000,000 708,497.33

44 CONCRETE BREAKER E44 290.0 20.0 m3/jam 900,000,000 866,426.41

45 ASPAHLT TANKER E45 190.0 4,000.0 liter 500,000,000 572,975.23

46 CEMENT TANKER E46 190.0 4,000.0 liter 500,000,000 531,375.23

47 CONDRETE MIXER (350) E47 20.0 350.0 liter 35,000,000 76,472.32

48 VIBRATING RAMMER E48 4.2 80.0 KG 20,000,000 44,729.05

49 TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 750,000,000 667,747.72

50 BORE PILE MACHINE E50 125.0 60.0 CM 1,170,000,000 726,465.84

51 CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 900,000,000 669,031.55

52 BLENDING EQUIPMENT E52 50.0 30.0 Ton 500,000,000 256,292.19

53 ASPHALT LIQUID MIXER E34a 40.0 20,000.0 Liter 15,000,000 106,361.75

Jakarta , 27 Maret 2016

PENAWAR

URAIAN ANALISA ALAT ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (I)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan ASPHALT MIXING PLANT E01 2. Tenaga Pw 294.0 HP 3. Kapasitas Cp 60.0 T/Jam 4. Alat a. Umur Ekonomis A 10.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam c. Harga Alat B 2,500,000,000.0 Rupiah

1

5 Kapastas tangki aspal Ca 30,000.00 liter

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 250,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.16275 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 244,118.09 Rupiah

W

b. Asuransi, dll = 0.1 x B F 166,666.67 RupiahW

Biaya Pasti per Jam = ( E + F ) G 410,784.76 Rupiah

C. BIAYA OPERASI PER JAM KERJA 1. Bahan Bakar = (12%-15%) x Pw x Ms H1 458,640.00 Rupiah

Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 5,241,600.00 Rupiah Khusus AMPdan aspal (Oil Heater)Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 312,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 264,600.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 145,833 W

4. Biaya perbaikan (12,5 % - 17,5 %) x B K 291,666.67 RupiahW

5 Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 26,362.29 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 6,753,883.43 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 7,164,668.19 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter

7 PPN diperhitungkan pada lembar Rekapitulasi ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (II)

Biaya Pekerjaan

8 Bahan bakar Batubara 700.00 Rp/kg

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan ASPHALT FINISHER E02 2. Tenaga Pw 72.4 HP 3. Kapasitas Cp 10.0 Ton 4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,400.0 Jam c. Harga Alat B 1,200,000,000 Rupiah

5.

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 120,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 177,125.69 Rupiah

W

b. Asuransi, dll = 0.1 x B F 85,714.29 RupiahW

Biaya Pasti per Jam = ( E + F ) G 262,839.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 112,944.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,160.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 53,571 W

3. Perawatan dan (12,5 % - 17,5 %) x B K 150,000.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 403,644.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 666,483.98 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan ASPHALT SPRAYER E03 2. Tenaga Pw 4.0 HP 3. Kapasitas Cp 850.0 Liter 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 121,000,000 Rupiah

5 Kapastas tangki aspal Ca 850 Liter

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 12,100,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 14,363.77 Rupiah

W

b. Asuransi, dll = 0.1 x B F 6,050.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 20,413.77 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 4,992.00 RupiahBahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 8,840.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 3,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 5,294 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 7,562.50 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 51,656.82 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 72,070.59 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan BULLDOZER 100-150 HP E04 2. Tenaga Pw 155.0 HP 3. Kapasitas Cp - - 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 700,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 70,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 83,096.21 Rupiah

W

b. Asuransi, dll = 0.1 x B F 35,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 118,096.21 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 193,440.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 116,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 30,625 W

3. Perawatan dan (12,5 % - 17,5 %) x B K 43,750.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 406,033.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 524,129.78 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan COMPRESSOR 4000-6500 L\M E05 2. Tenaga Pw 60.0 HP 3. Kapasitas Cp 5,000.0 CPM/(L/m) 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 110,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 11,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 13,057.98 Rupiah

W

b. Asuransi, dll = 0.1 x B F 5,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 18,557.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 74,880.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 45,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 4,813 W

3. Perawatan dan (12,5 % - 17,5 %) x B K 6,875.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 153,536.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 172,094.05 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06 2. Tenaga Pw 20.0 HP 3. Kapasitas Cp 500.0 Liter 4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam c. Harga Alat B 175,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 17,550,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.57619 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 60,672.86 Rupiah

W

b. Asuransi, dll = 0.1 x B F 11,700.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 72,372.86 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 18,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 10,238 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 20,475.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 101,881.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 174,253.93 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan DUMP TRUCK 3.5 TON E08 2. Tenaga Pw 100.0 HP 3. Kapasitas Cp 3.5 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 200,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 20,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 23,741.77 Rupiah

W

b. Asuransi, dll = 0.1 x B F 10,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 33,741.77 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 124,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 75,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 8,750 W

3. Perawatan dan (12,5 % - 17,5 %) x B K 12,500.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 243,018.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 276,760.34 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir / Mekanik U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan DUMP TRUCK 10 TON E09 2. Tenaga Pw 200.0 HP 3. Kapasitas Cp 8.0 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 300,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 30,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 35,612.66 Rupiah

W

b. Asuransi, dll = 0.1 x B F 15,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 50,612.66 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 249,600.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 150,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 13,125 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 18,750.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 453,443.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 504,056.23 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir / Mekanik U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan EXCAVATOR 80-140 HP E10 2. Tenaga Pw 133.0 HP 3. Kapasitas Cp 0.93 M3 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 800,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 80,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 94,967.09 Rupiah

W

b. Asuransi, dll = 0.1 x B F 40,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 134,967.09 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 165,984.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 99,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 35,000 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 50,000.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 372,702.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 507,669.66 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 E11 2. Tenaga Pw 190.0 HP 3. Kapasitas Cp 10.0 M3 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 330,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 33,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 39,173.93 Rupiah

W

b. Asuransi, dll = 0.1 x B F 16,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 55,673.93 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 237,120.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 142,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 14,438 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 20,625.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 436,651.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 492,325.00 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan GENERATOR SET E12 2. Tenaga Pw 180.0 HP 3. Kapasitas Cp 135.0 KVA 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 207,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 20,700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 24,572.74 Rupiah

W

b. Asuransi, dll = 0.1 x B F 10,350.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 34,922.74 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 224,640.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 135,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 9,056 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 12,937.50 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 403,602.32 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 438,525.06 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan MOTOR GRADER >100 HP E13 2. Tenaga Pw 135.0 HP 3. Kapasitas Cp 10,800.0 - 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 900,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 90,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 106,837.98 Rupiah

W

b. Asuransi, dll = 0.1 x B F 45,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 151,837.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 168,480.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 101,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 39,375 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 56,250.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 387,323.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 539,161.55 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15 2. Tenaga Pw 96.0 HP 3. Kapasitas Cp 1.5 M3 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 900,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 90,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 106,837.98 Rupiah

W

b. Asuransi, dll = 0.1 x B F 45,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 151,837.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 119,808.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 72,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 39,375 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 56,250.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 309,401.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 461,239.55 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T E16 2. Tenaga Pw 55.0 HP 3. Kapasitas Cp 8.0 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 350,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 35,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 41,548.10 Rupiah

W

b. Asuransi, dll = 0.1 x B F 17,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 59,048.10 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 68,640.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 41,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15,313 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 21,875.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 169,046.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 228,094.17 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17 2. Tenaga Pw 82.0 HP 3. Kapasitas Cp 8.1 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 750,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 75,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 89,031.65 Rupiah

W

b. Asuransi, dll = 0.1 x B F 37,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 126,531.65 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 102,336.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 61,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 32,813 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 46,875.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 265,492.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 392,023.72 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan TIRE ROLLER 8-10 T. E18 2. Tenaga Pw 100.5 HP 3. Kapasitas Cp 9.0 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 700,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 70,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 83,096.21 Rupiah

W

b. Asuransi, dll = 0.1 x B F 35,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 118,096.21 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 125,424.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 75,375.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 30,625 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 43,750.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 297,142.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 415,238.78 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19 2. Tenaga Pw 82.0 HP 3. Kapasitas Cp 7.050 Ton 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 600,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 71,225.32 Rupiah

W

b. Asuransi, dll = 0.1 x B F 30,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 101,225.32 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 102,336.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 61,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 26,250 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 37,500.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 249,554.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 350,779.89 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan CONCRETE VIBRATOR E20 2. Tenaga Pw 5.5 HP 3. Kapasitas Cp 25.0 - 4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam c. Harga Alat B 4,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 1,135.69 Rupiah

W

b. Asuransi, dll = 0.1 x B F 400.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 1,535.69 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 8,580.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,950.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 250 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 700.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 36,448.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 37,984.27 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan STONE CRUSHER E21 2. Tenaga Pw 220.0 HP 3. Kapasitas Cp 50.0 T/Jam 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 1,500,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 150,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 178,063.30 Rupiah

W

b. Asuransi, dll = 0.1 x B F 75,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 253,063.30 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 274,560.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 165,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 65,625 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 93,750.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 2 Orang / Jam ) x U2 M 17,574.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 629,691.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 882,754.30 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan WATER PUMP 70-100 mm E22 2. Tenaga Pw 6.0 HP 3. Kapasitas Cp - - 4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 5,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 904.76 Rupiah

W

b. Asuransi, dll = 0.1 x B F 250.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 1,154.76 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 7,488.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 219 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 312.50 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 34,487.82 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 35,642.58 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan WATER TANKER 3000-4500 L. E23 2. Tenaga Pw 100.0 HP 3. Kapasitas Cp 4,000.0 Liter 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 90,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 9,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 10,683.80 Rupiah

W

b. Asuransi, dll = 0.1 x B F 4,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 15,183.80 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 124,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 75,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 3,938 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 5,625.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 231,331.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 246,514.87 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan PEDESTRIAN ROLLER E24 2. Tenaga Pw 8.8 HP 3. Kapasitas Cp 835.000 Ton 4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 150,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 15,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 27,142.75 Rupiah

W

b. Asuransi, dll = 0.1 x B F 7,500.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 34,642.75 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 10,982.40 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 6,600.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 6,563 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 9,375.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 55,488.47 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 90,131.22 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan TAMPER E25 2. Tenaga Pw 4.7 HP 3. Kapasitas Cp 121.000 Ton 4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam c. Harga Alat B 17,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 1,700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 4,826.70 Rupiah

W

b. Asuransi, dll = 0.1 x B F 1,700.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 6,526.70 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 7,332.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,230.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 1,063 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 2,975.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 37,568.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 44,094.77 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan JACK HAMMER E26 2. Tenaga Pw 0.0 HP 3. Kapasitas Cp 1,330.000 - 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 35,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 3,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 4,154.81 Rupiah

W

b. Asuransi, dll = 0.1 x B F 1,750.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 5,904.81 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 0.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 0.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 1,531 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 2,187.50 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 25,687.32 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 31,592.13 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan WELDING SET E32 2. Tenaga Pw 40.0 HP 3. Kapasitas Cp 250.00 Amp 4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 17,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 1,750,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 2,077.41 Rupiah

W

b. Asuransi, dll = 0.1 x B F 875.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 2,952.41 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 49,920.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 30,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 766 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 1,093.75 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 103,747.95 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 106,700.35 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN 1. Jenis Peralatan BORE PILE MACHINE E33 2. Tenaga Pw 150.0 HP 3. Kapasitas Cp 2,000.00 Meter 4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam c. Harga Alat B 2,000,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B C 200,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -(1 + i)^A - 1

3. Biaya Pasti per Jam :a. Biaya Pengembalian Modal = ( B - C ) x D E 206,646.64 Rupiah

W

b. Asuransi, dll = 0.1 x B F 100,000.00 RupiahW

Biaya Pasti per Jam = ( E + F ) G 306,646.64 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 187,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 112,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 87,500 Rupiah W

3. Perawatan dan (12,5 % - 17,5 %) x B K 125,000.00 Rupiah perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 13,181.14 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,787.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 534,168.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 840,815.21 Rupiah

E. LAIN - LAIN 1. Tingkat Suku Bunga i 10.00 % / Tahun 2. Upah Operator / Sopir U1 13,181.14 Rp./Jam 3. Upah Pembantu Operator / Pmb.Sopir U2 8,787.43 Rp./Jam 4. Bahan Bakar Bensin Mb 8,000.00 Liter 5. Bahan Bakar Solar Ms 10,400.00 Liter 6. Minyak Pelumas Mp 30,000.00 Liter 7. PPN diperhitungkan pada lembar Rekapitulasi

Biaya Pekerjaan