ANALISA HARGA SATUAN PEKERJAAN MEDAN Kota : Medan No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP) I PEKERJAAN PERSIAPAN 1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M a Tiang kayu borneo 4/6 0.05 m 3 5,400,000.00 270,000.00 b Semen PC (abu-abu) 0.05 sak 54,000.00 2,700.00 c Seng gelombang 1.20 sak 57,500.00 69,000.00 d Pasir beton 0.01 m 3 92,000.00 460.00 e Split (batu pecah) 0.01 m 3 270,000.00 2,430.00 f Balok kayu borneo 4/6 0.05 m 3 5,400,000.00 270,000.00 g Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00 h Meni Besi 0.45 kg 22,000.00 9,900.00 i Tukang kayu 0.20 org 87,500.00 17,500.00 j Pembantu tukang 0.10 org 50,000.00 5,000.00 Jumlah 648,040.00 Dibulatkan 648,040.00 2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M a Tiang kayu borneo 4/6 0.05 m 3 5,400,000.00 270,000.00 b Semen PC (abu-abu) 0.04 sak 54,000.00 2,160.00 c Kawat Duri 2.50 kg 155,000.00 387,500.00 d Pasir beton 0.01 m 3 92,000.00 460.00 e Split (batu pecah) 0.01 m 3 270,000.00 2,430.00 f Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00 g Tukang kayu 0.20 org 87,500.00 17,500.00 h Pembantu tukang 0.30 org 50,000.00 15,000.00

Upload: junaidiazaid

Post on 30-Dec-2015

471 views

Category:

Documents


5 download

DESCRIPTION

RAB

TRANSCRIPT

Page 1: 166742630 Analisa Harga Satuan Pekerjaan Medan

ANALISA HARGA SATUAN PEKERJAAN MEDAN

Kota : Medan

No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)

I PEKERJAAN PERSIAPAN

1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M

a Tiang kayu borneo 4/6 0.05 m

3 5,400,000.00 270,000.00

b Semen PC (abu-abu) 0.05 sak 54,000.00 2,700.00

c Seng gelombang 1.20 sak 57,500.00 69,000.00

d Pasir beton 0.01 m

3 92,000.00 460.00

e Split (batu pecah) 0.01 m

3 270,000.00 2,430.00

f Balok kayu borneo 4/6 0.05 m

3 5,400,000.00 270,000.00

g Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00

h Meni Besi 0.45 kg 22,000.00 9,900.00

i Tukang kayu 0.20 org 87,500.00 17,500.00

j Pembantu tukang 0.10 org 50,000.00 5,000.00

Jumlah 648,040.00

Dibulatkan 648,040.00

2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M

a Tiang kayu borneo 4/6 0.05 m

3 5,400,000.00 270,000.00

b Semen PC (abu-abu) 0.04 sak 54,000.00 2,160.00

c Kawat Duri 2.50 kg 155,000.00 387,500.00

d Pasir beton 0.01 m

3 92,000.00 460.00

e Split (batu pecah) 0.01 m

3 270,000.00 2,430.00

f Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00

g Tukang kayu 0.20 org 87,500.00 17,500.00

h Pembantu tukang 0.30 org 50,000.00 15,000.00

Page 2: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 696,100.00

Dibulatkan 696,100.00

3 1 M

1 PENGUKURAN & PEMASANGAN BOWPLANK

a Kayu kaso 5/7 borneo 0.02 m

3 5,400,000.00 108,000.00

b Paku 5 - 10 cm 0.02 kg 17,500.00 350.00

c Papan papan kayu terentang 2/20 0.00 m

3 1,448,200.00 5,792.80

d Tukang kayu 0.10 org 87,500.00 8,750.00

e Pembantu tukang 0.10 org 50,000.00 5,000.00

Jumlah 127,892.80

Dibulatkan 127,890.00

4 1 M

2 PEMBUATAN KANTOR DIREKSI

a Kayu kaso 5/7 borneo 0.02 m

3 5,400,000.00 108,000.00

b Papan kayu terentang 0.18 m

3 1,448,200.00 260,676.00

c Paku semua ukuran 0.85 kg 17,500.00 14,875.00

d Besi strip 1.10 kg 14,100.00 15,510.00

e Semen PC (abu-abu) 35.00 kg 54,000.00 1,890,000.00

f Pasir pasang 0.15 m

3 84,000.00 12,600.00

g Pasir beton 0.10 m

3 92,000.00 9,200.00

h Split (batu pecah) 0.15 m

3 270,000.00 40,500.00

i Bata merah 30.00 bh 650.00 19,500.00

j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 61,750.00 74,100.00

k Seng Plat BJLS 32 1.00 m

2 33,300.00 33,300.00

l Kawat harmonika 2.00 m

2 24,500.00 49,000.00

m Kaca polos 3 mm 0.08 m

2 90,000.00 7,200.00

n Kunci tanam standart 0.15 bh 55,000.00 8,250.00

o Triplek 120 x 240 x 0,4 cm 0.06 lbr 53,750.00 3,225.00

p Tukang kayu 2.00 org 87,500.00 175,000.00

q Tukang batu 1.00 org 87,500.00 87,500.00

r Pembantu tukang 2.00 org 50,000.00 100,000.00

Jumlah 2,908,436.00

Page 3: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 2,908,430.00

5 1 M

2 PEMBUATAN GUDANG PROYEK

a Kayu kaso 5/7 borneo 0.02 m

3 5,400,000.00 108,000.00

b Papan kayu terentang 0.10 m

3 1,448,200.00 144,820.00

c Paku 0.30 kg 17,500.00 5,250.00

d Semen PC (abu-abu) 0.21 sak 54,000.00 11,340.00

e Pasir beton 0.03 m

3 92,000.00 2,760.00

f Split (batu pecah) 0.05 m

3 270,000.00 13,500.00

g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 61,750.00 74,100.00

h Tukang kayu 1.00 org 87,500.00 87,500.00

i Pembantu tukang 1.00 org 50,000.00 50,000.00

Jumlah 497,270.00

Dibulatkan 497,270.00

6 1 M

2 MEMBERSIHKAN LOKASI ROYEK

a Pembantu tukang 0.10 org 50,000.00 5,000.00

Jumlah 5,000.00

Dibulatkan 5,000.00

7 1 M

2 MEMBERSIHKAN PUING-PUING

a Pembantu tukang 0.20 org 50,000.00 10,000.00

Jumlah 10,000.00

Dibulatkan 10,000.00

8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN

a Pembantu tukang 2.00 org 50,000.00 100,000.00

Jumlah 100,000.00

Dibulatkan 100,000.00

9 1M

2 PEMBUATAN JALAN MASUK PROYEK

a Batu belah 15/20 0.10 m

3 128,200.00 12,820.00

b Koral 5/7 ( sirtu ) 0.05 m

3 82,000.00 4,100.00

c Pasir urug 0.01 m

3 67,000.00 670.00

d Pembantu tukang 1.00 org 50,000.00 50,000.00

Page 4: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 67,590.00

Dibulatkan 67,500.00

10 1 M

3 PEMBONGKARAN BETON

a Pembantu tukang 6.20 org 50,000.00 310,000.00

Jumlah 310,000.00

Dibulatkan 310,000.00

11 1 M

3 PEMBONGKARAN DINDING BATA

a Pembantu tukang 4.60 org 50,000.00 230,000.00

Jumlah 230,000.00

Dibulatkan 230,000.00

12 1 M

2 PEKERJAAN PAGAR PAPAN RANGKA BALOK

a Papan kayu borneo 0.02 m

3 5,660,000.00 113,200.00

b Balok kayu borneo 5/7 0.02 m

3 5,400,000.00 108,000.00

c Pasir beton 0.08 m

3 92,000.00 7,360.00

d Split (batu pecah) 0.15 m

3 270,000.00 40,500.00

e Semen abu - abu 0.50 sak 54,000.00 27,000.00

f Tukang kayu 0.13 org 87,500.00 11,375.00

g Pembantu tukang 0.38 org 50,000.00 19,000.00

Jumlah 326,435.00

Dibulatkan 326,400.00

II PEKERJAAN TANAH

1 1 M

3 GALIAN TANAH SEDALAM 1 M

a Pembantu tukang 0.40 org 50,000.00 20,000.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 21,500.00

Dibulatkan 21,500.00

2 1 M

3 GALIAN TANAH SEDALAM 2 M

Page 5: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Pembantu tukang 0.53 org 50,000.00 26,500.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 28,000.00

Dibulatkan 28,000.00

3 1 M

3 GALIAN TANAH SEDALAM 3 M

a Pembantu tukang 0.74 org 50,000.00 37,000.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 38,500.00

Dibulatkan 38,500.00

4 1 M

3 GALIAN TANAH KERAS SEDALAM 1 M

a Pembantu tukang 0.45 org 50,000.00 22,500.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 24,000.00

Dibulatkan 24,000.00

5 1 M

2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM

a Pembantu tukang 0.05 org 50,000.00 1,250.00

b Tukang gali 0.02 org 75,000.00 1,125.00

Jumlah 2,375.00

Dibulatkan 2,370.00

6 1 M

3 PEMBUANGAN TANAH SEJAUH 150 M

a Pembantu tukang 0.42 org 50,000.00 21,000.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 22,500.00

Dibulatkan 22,500.00

7 1 M

3 URUGAN TANAH KEMBALI

a Pembantu tukang 0.19 org 50,000.00 9,500.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 11,000.00

Dibulatkan 11,000.00

8 1 M

3 PEMADATAN TANAH

Page 6: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Pembantu tukang 0.50 org 50,000.00 25,000.00

b Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 26,500.00

Dibulatkan 26,500.00

9 1 M

3 URUGAN PASIR

a Pasir urug 1.20 m

3 67,000.00 80,400.00

b Pembantu tukang 0.30 org 50,000.00 15,000.00

c Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 96,900.00

Dibulatkan 96,900.00

10 1 M

3 URUGAN TANAH

a Tanah urug 1.20 m

3 78,000.00 93,600.00

b Pembantu tukang 0.30 org 50,000.00 15,000.00

c Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 110,100.00

Dibulatkan 110,100.00

11 1 M

3 URUGAN SIRTU

a Sirtu ( koral ) 1.20 m

3 82,000.00 98,400.00

b Pembantu tukang 0.25 org 50,000.00 12,500.00

c Tukang gali 0.02 org 75,000.00 1,500.00

Jumlah 112,400.00

Dibulatkan 112,400.00

III PEKERJAAN PONDASI

1 1 M

3 PASANG PONDASI BT KALI , 1 Pc : 3 Ps

a Batu belah 1.10 m

3 128,200.00 141,020.00

b Semen PC (abu-abu) 4.04 sak 54,000.00 218,160.00

c Pasir pasang 0.49 m

3 84,000.00 40,740.00

Page 7: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Pembantu tukang 1.50 org 50,000.00 75,000.00

e Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 527,420.00

Dibulatkan 527,420.00

2 1 M

3 PASANG PONDASI BT KALI , 1 Pc : 4 Ps

a Batu belah 1.10 m

3 128,200.00 141,020.00

b Semen PC (abu-abu) 3.26 sak 54,000.00 176,040.00

c Pasir pasang 0.52 m

3 84,000.00 43,680.00

d Pembantu tukang 1.50 org 50,000.00 75,000.00

e Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 488,240.00

Dibulatkan 488,240.00

3 1 M

3 PASANG PONDASI BT KALI , 1 Pc : 5 Ps

a Batu belah 1.10 m

3 128,200.00 141,020.00

b Semen PC (abu-abu) 2.72 sak 54,000.00 146,880.00

c Pasir pasang 0.54 m

3 84,000.00 45,696.00

d Pembantu tukang 1.50 org 50,000.00 75,000.00

e Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 461,096.00

Dibulatkan 461,090.00

4 1 M

3 PASANG PONDASI BATU KOSONG ( AANSTAMPING )

a Batu belah 1.20 m

3 128,200.00 153,840.00

b Pasir urug 0.30 m

3 67,000.00 20,100.00

c Pembantu tukang 0.78 org 50,000.00 39,000.00

d Tukang batu 0.39 org 87,500.00 34,125.00

Jumlah 247,065.00

Dibulatkan 247,000.00

5 1 M

3 MEMBUAT BETON BERTULANG UNTUK PONDASI 1 Pc : 2 Ps : 3 Kr

a Semen PC (abu-abu) 6.72 sak 54,000.00 362,880.00

b Pasir beton 0.54 m

3 92,000.00 49,680.00

Page 8: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Split (batu pecah) 0.81 m

3 270,000.00 218,700.00

d Pembantu tukang 2.00 org 50,000.00 100,000.00

e Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 761,885.00

Dibulatkan 761,800.00

6 1 Kg PENULANGAN BETON PONDASI

a Besi beton polos 1.05 kg 13,950.00 14,647.50

b Kawat beton 0.02 kg 13,400.00 201.00

c Pembantu tukang 0.01 org 50,000.00 350.00

d Tukang besi 0.01 org 87,500.00 612.50

Jumlah 15,811.00

Dibulatkan 15,800.00

7 1 M

2 PEKERJAAN BEKISTING UNTUK PONDASI

a Papan kayu terentang 0.04 m

3 1,448,200.00 57,928.00

b Paku 5 - 12 cm 0.30 kg 1,900.00 570.00

c Pelumas begisting (oli/minyak) 0.10 Ltr 12,500.00 1,250.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang kayu 0.26 org 87,500.00 22,750.00

Jumlah 97,498.00

Dibulatkan 97,400.00

8 1 M

3 PASANG PONDASI CYCLOOP (60 %BETON : 40% BATU KALI)

a Besi beton polos 50.00 kg 13,950.00 697,500.00

b Semen PC (abu-abu) 4.04 sak 54,000.00 218,160.00

c Pasir beton 0.32 m

3 92,000.00 29,440.00

d Split (batu pecah) 0.49 m

3 270,000.00 132,300.00

e Kawat beton 0.80 kg 13,400.00 10,720.00

f Batu belah 0.40 m

3 128,200.00 51,280.00

g Pembantu tukang 2.00 org 50,000.00 100,000.00

h Tukang batu 0.85 org 87,500.00 74,375.00

Jumlah 1,313,775.00

Page 9: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 1,313,700.00

9 1 M

3 PASANG PONDASI SUMURAN DIAMETER 100 cm

a Batu belah 0.45 m

3 128,200.00 57,690.00

b Semen PC (abu-abu) 5.60 sak 54,000.00 302,400.00

c Pasir beton 0.45 m

3 92,000.00 41,400.00

d Split (batu pecah) 0.67 m

3 270,000.00 180,900.00

e Pembantu tukang 2.38 org 50,000.00 119,000.00

f Tukang batu 0.30 org 87,500.00 26,250.00

Jumlah 727,640.00

Dibulatkan 727,600.00

10 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm

a Pasir beton 0.10 m

3 92,000.00 9,200.00

b Split (batu pecah) 0.15 m

3 270,000.00 40,500.00

c Semen PC (abu-abu) 1.21 sak 54,000.00 65,340.00

d Besi beton polos 45.00 kg 13,950.00 627,750.00

e Kawat beton 0.90 kg 13,400.00 12,060.00

f Balok kayu borneo super 5/7 0.03 m

3 5,400,000.00 172,800.00

g Papan kayu terentang 0.01 m

3 5,660,000.00 56,600.00

h Paku 5 - 12 cm 0.12 kg 17,500.00 2,100.00

i Pelumas begisting (oli/minyak) 0.09 Ltr 12,500.00 1,125.00

j Plamir tembok 0.24 kg 25,000.00 6,000.00

k Pembantu tukang 1.00 org 50,000.00 50,000.00

l Tukang batu 0.67 org 87,500.00 58,625.00

Jumlah 1,102,100.00

Dibulatkan 1,102,100.00

11 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM

a Pasir beton 0.08 m

3 92,000.00 7,360.00

b Split (batu pecah) 0.13 m

3 270,000.00 35,100.00

c Semen PC (abu-abu) 0.98 sak 54,000.00 52,920.00

d Besi beton polos 34.50 kg 13,950.00 481,275.00

Page 10: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Kawat beton 0.70 kg 13,400.00 9,380.00

f Balok kayu borneo super 5/7 0.03 m

3 5,400,000.00 162,000.00

g Papan kayu terentang 0.01 m

3 5,660,000.00 56,600.00

h Paku 5 - 12 cm 0.12 kg 17,500.00 2,100.00

i Pelumas begisting (oli/minyak) 0.09 Ltr 12,500.00 1,125.00

j Plamir tembok 0.20 kg 25,000.00 5,000.00

k Pembantu tukang 0.80 org 50,000.00 40,000.00

l Tukang batu 0.50 org 87,500.00 43,750.00

Jumlah 896,610.00

Dibulatkan 896,600.00

12 1 M

3 MEMBUAT PONDASI TIANG PANCANG UKURAN 25 X 25

a Pasir beton 0.06 m

3 92,000.00 5,520.00

b Split (batu pecah) 0.11 m

3 270,000.00 29,700.00

c Semen PC (abu-abu) 0.82 sak 54,000.00 44,280.00

d Besi beton polos 34.50 kg 13,950.00 481,275.00

e Kawat beton 0.60 kg 13,400.00 8,040.00

f Balok kayu borneo super 5/7 0.03 m

3 5,400,000.00 162,000.00

g Papan kayu terentang 0.01 m

3 5,660,000.00 56,600.00

h Paku 5 - 12 cm 0.11 kg 17,500.00 1,925.00

i Pelumas begisting (oli/minyak) 0.08 Ltr 12,500.00 1,000.00

j Plamir tembok 0.20 kg 25,000.00 5,000.00

k Pembantu tukang 0.80 org 50,000.00 40,000.00

l Tukang batu 0.50 org 87,500.00 43,750.00

Jumlah 879,090.00

Dibulatkan 879,000.00

13 1 M

3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )

a Papan kayu terentang 0.20 m

3 1,448,200.00 289,640.00

b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00

c Pelumas begisting (oli/minyak) 0.40 Ltr 12,500.00 5,000.00

d Besi beton polos 125.00 kg 13,950.00 1,743,750.00

Page 11: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Kawat beton 2.25 kg 13,400.00 30,150.00

f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 3.90 org 50,000.00 195,000.00

j Tukang batu 0.35 org 87,500.00 30,625.00

k Tukang kayu 1.04 org 87,500.00 91,000.00

l Tukang besi 1.05 org 87,500.00 91,875.00

Jumlah 3,110,570.00

Dibulatkan 3,110,500.00

14 1 M

3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )

a Papan kayu terentang 0.20 m

3 1,448,200.00 289,640.00

b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00

c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00

d Besi beton polos Polos 150.00 kg 13,950.00 2,092,500.00

e Kawat beton 2.25 kg 13,400.00 30,150.00

f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 4.00 org 50,000.00 200,000.00

j Tukang batu 0.40 org 87,500.00 35,000.00

k Tukang kayu 1.00 org 87,500.00 87,500.00

l Tukang besi 1.00 org 87,500.00 87,500.00

Jumlah 3,460,820.00

Dibulatkan 3,460,800.00

15 1 M

3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )

a Papan kayu terentang 0.20 m

3 1,448,200.00 289,640.00

b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00

c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00

d Besi beton polos Polos 125.00 kg 13,950.00 1,743,750.00

Page 12: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Kawat beton 2.10 kg 13,400.00 28,140.00

f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 3.90 org 50,000.00 195,000.00

j Tukang batu 0.40 org 87,500.00 35,000.00

k Tukang kayu 1.00 org 87,500.00 87,500.00

l Tukang besi 1.00 org 87,500.00 87,500.00

Jumlah 3,105,060.00

Dibulatkan 3,105,000.00

16 1 M

3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )

a Papan kayu terentang 0.20 m

3 1,448,200.00 289,640.00

b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00

c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00

d Besi beton polos 150.00 kg 13,950.00 2,092,500.00

e Kawat beton 2.25 kg 13,400.00 30,150.00

f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 4.00 org 50,000.00 200,000.00

j Tukang batu 0.40 org 87,500.00 35,000.00

k Tukang kayu 1.00 org 87,500.00 87,500.00

l Tukang besi 1.00 org 87,500.00 87,500.00

Jumlah 3,460,820.00

Dibulatkan 3,460,800.00

IV

PEKERJAAN BETON NON STRUKTUR DAN BETON

STRUKTUR

Page 13: 166742630 Analisa Harga Satuan Pekerjaan Medan

A PEKERJAAN BETON

1 1 M

3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt

a Semen PC (abu-abu) 4.36 sak 54,000.00 235,440.00

b Pasir beton 0.52 m3 92,000.00 47,840.00

c Split (batu pecah) 0.87 m

3 270,000.00 234,900.00

d Pembantu tukang 2.00 org 50,000.00 100,000.00

e Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 648,805.00

Dibulatkan 648,800.00

2 1 M

3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt

a Semen PC (abu-abu) 4.64 sak 54,000.00 250,560.00

b Pasir beton 0.52 m

3 92,000.00 47,840.00

c Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

d Pembantu tukang 2.00 org 50,000.00 100,000.00

e Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 639,625.00

Dibulatkan 639,600.00

3 1 M

3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt

a Semen PC (abu-abu) 6.72 sak 54,000.00 362,880.00

b Pasir beton 0.54 m

3 92,000.00 49,680.00

c Split (batu pecah) 0.81 m

3 270,000.00 218,700.00

d Pembantu tukang 2.00 org 50,000.00 100,000.00

e Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 761,885.00

Dibulatkan 761,800.00

4 1 M

3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225

a Semen PC (abu-abu) 7.76 sak 54,000.00 419,040.00

b Pasir beton 0.65 m

3 92,000.00 59,800.00

c Split (batu pecah) 0.65 m

3 270,000.00 175,500.00

d Pembantu tukang 2.00 org 50,000.00 100,000.00

Page 14: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 784,965.00

Dibulatkan 784,900.00

5 1 M

3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275

a Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00

b Pasir beton 0.55 m

3 92,000.00 50,600.00

c Split (batu pecah) 0.70 m

3 270,000.00 189,000.00

d Pembantu tukang 2.02 org 50,000.00 101,000.00

e Tukang batu 0.40 org 87,500.00 35,000.00

Jumlah 807,600.00

Dibulatkan 807,600.00

B PEKERJAAN PEMBESIAN

1 1 KG PENULANGAN BETON/BESI BETON POLOS

a Besi beton polos 1.05 kg 13,950.00 14,647.50

b Kawat beton 0.02 kg 13,400.00 268.00

c Pembantu tukang 0.01 org 50,000.00 500.00

d Tukang besi 0.01 org 87,500.00 875.00

Jumlah 16,290.50

Dibulatkan 16,200.00

2 1 KG PENULANGAN BETON/BESI BETON ULIR

a Besi Beton Ulir 1.10 kg 15,100.00 16,610.00

b Kawat beton 0.02 kg 13,400.00 201.00

c Pembantu tukang 0.01 org 50,000.00 500.00

d Tukang besi 0.02 org 87,500.00 1,750.00

Jumlah 19,061.00

Dibulatkan 19,000.00

C PEKERJAAN BEGISTING

1 1 M

2 PASANG BEKISTING UNTUK SLOOF

a Papan kayu terentang 0.05 m

3 1,448,200.00 65,169.00

b Paku 5 - 12 cm 0.30 kg 17,500.00 5,250.00

Page 15: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Pelumas begisting (oli/minyak) 0.10 Ltr 12,500.00 1,250.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang kayu 0.26 org 87,500.00 22,750.00

Jumlah 109,419.00

Dibulatkan 109,400.00

2 1 M

2 PASANG BEKISTING UNTUK KOLOM

a Papan kayu terentang 0.04 m

3 1,448,200.00 57,928.00

b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00

c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00

d Balok Kayu Borneo 0.04 m

3 5,400,000.00 216,000.00

e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50

f Pembantu tukang 0.30 org 50,000.00 15,000.00

g Tukang kayu 0.33 org 87,500.00 28,875.00

Jumlah 369,635.50

Dibulatkan 369,600.00

3 1M

2 PASANG BEKISTING UNTUK BALOK

a Papan kayu terentang 0.04 m

3 1,448,200.00 57,928.00

b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00

c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00

d Balok Kayu Borneo 0.04 m

3 5,400,000.00 216,000.00

e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50

f Pembantu tukang 0.32 org 50,000.00 16,000.00

g Tukang kayu 0.33 org 87,500.00 28,875.00

Jumlah 370,635.50

Dibulatkan 370,600.00

4 1 M

2 PASANG BEKISTING UNTUK PLAT LANTAI

a Papan kayu terentang 0.04 m

3 1,448,200.00 57,928.00

b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00

c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00

d Balok Kayu Borneo 0.04 m

3 5,400,000.00 216,000.00

Page 16: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50

f Pembantu tukang 0.32 org 50,000.00 16,000.00

g Tukang kayu 0.33 org 87,500.00 28,875.00

Jumlah 370,635.50

Dibulatkan 370,600.00

5 1 M

2 PASANG BEKISTING UNTUK TANGGA

a Papan kayu terentang 0.03 m

3 1,448,200.00 43,446.00

b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00

c Pelumas begisting (oli/minyak) 0.15 Ltr 12,500.00 1,875.00

d Balok kayu borneo 0.02 m

3 5,400,000.00 108,000.00

e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50

f Pembantu tukang 0.32 org 50,000.00 16,000.00

g Tukang kayu 0.33 org 87,500.00 28,875.00

Jumlah 247,528.50

Dibulatkan 247,500.00

D PEKERJAAN BETON BERTULANG

1 1 M

3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225

a Papan kayu terentang 0.27 m

3 1,448,200.00 391,014.00

b Paku 5 - 12 cm 2.00 kg 17,500.00 35,000.00

c Pelumas begisting (oli/minyak) 0.60 Ltr 12,500.00 7,500.00

d Besi beton polos 200.00 kg 13,950.00 2,790,000.00

e Kawat beton 3.00 kg 13,400.00 40,200.00

f Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 4.50 org 50,000.00 225,000.00

j Tukang batu 0.35 org 87,500.00 30,625.00

k Tukang kayu 1.56 org 87,500.00 136,500.00

l Tukang besi 1.40 org 87,500.00 122,500.00

Jumlah 4,468,779.00

Page 17: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 4,468,700.00

2 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 125.00 kg 13,950.00 1,743,750.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 5,996,520.00

Dibulatkan 5,996,500.00

3 1 M

3 MEMBUAT KOLOM BETON BERTULANG (150 kg BESI + BEKISTING)

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 150.00 kg 13,950.00 2,092,500.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

Page 18: 166742630 Analisa Harga Satuan Pekerjaan Medan

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 6,345,270.00

Dibulatkan 6,345,200.00

4 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 160.00 kg 13,950.00 2,232,000.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 6,484,770.00

Dibulatkan 6,484,700.00

5 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 175.00 kg 13,950.00 2,441,250.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

Page 19: 166742630 Analisa Harga Satuan Pekerjaan Medan

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 6,694,020.00

Dibulatkan 6,694,000.00

6 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 200.00 kg 13,950.00 2,790,000.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 7,042,770.00

Dibulatkan 7,042,700.00

7 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

Page 20: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Besi beton polos 250.00 kg 13,950.00 3,487,500.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 7,740,270.00

Dibulatkan 7,740,200.00

8 1 M

3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m

3 1,448,200.00 579,280.00

b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00

c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00

d Besi beton polos 300.00 kg 13,950.00 4,185,000.00

e Kawat beton 4.50 kg 13,400.00 60,300.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00

k Pembantu tukang 7.30 org 50,000.00 365,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 3.30 org 87,500.00 288,750.00

n Tukang besi 2.10 org 87,500.00 183,750.00

Jumlah 8,437,770.00

Dibulatkan 8,437,700.00

Page 21: 166742630 Analisa Harga Satuan Pekerjaan Medan

9 1 M

3 MEMBUAT BALOK BETON BERTULANG ( 125 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m

3 1,448,200.00 463,424.00

b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00

c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00

d Besi beton polos 125.00 kg 13,950.00 1,743,750.00

e Kawat beton 2.25 kg 13,400.00 30,150.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.12 m

3 5,400,000.00 648,000.00

j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00

k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,000.00 256,000.00

l Pembantu tukang 5.80 org 50,000.00 290,000.00

m Tukang batu 0.35 org 87,500.00 30,625.00

n Tukang kayu 2.80 org 87,500.00 245,000.00

o Tukang besi 1.05 org 87,500.00 91,875.00

Jumlah 4,820,224.00

Dibulatkan 4,820,200.00

10 1 M

3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m

3 1,448,200.00 463,424.00

b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00

c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00

d Besi beton polos 150.00 kg 13,950.00 2,092,500.00

e Kawat beton 2.25 kg 10,000.00 22,500.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 10,000.00 7,800.00

i Balok kayu Borneo Super 0.12 m

3 5,400,000.00 648,000.00

j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00

k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,000.00 256,000.00

Page 22: 166742630 Analisa Harga Satuan Pekerjaan Medan

l Pembantu tukang 5.80 org 50,000.00 290,000.00

m Tukang batu 0.35 org 87,500.00 30,625.00

n Tukang kayu 2.80 org 87,500.00 245,000.00

o Tukang besi 1.05 org 87,500.00 91,875.00

Jumlah 4,958,524.00

Dibulatkan 4,958,500.00

11 1 M

3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m

3 1,448,200.00 463,424.00

b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00

c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00

d Besi beton polos 200.00 kg 13,950.00 2,790,000.00

e Kawat beton 3.00 kg 13,400.00 40,200.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 140,000.00 109200

i Balok kayu Borneo Super 0.14 m

3 4,000,000.00 560,000.00

j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00

k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 18,000.00 288,000.00

l Pembantu tukang 5.96 org 27,500.00 163,900.00

m Tukang batu 0.35 org 42,000.00 14,700.00

n Tukang kayu 2.80 org 42,000.00 117,600.00

o Tukang besi 1.40 org 42,000.00 58,800.00

Jumlah 5,371,964.00

Dibulatkan 5,371,900.00

12 1 M

3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)

a Papan kayu terentang 0.32 m

3 1,750,000.00 560,000.00

b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00

c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00

d Besi beton polos 225.00 kg 8,750.00 1,968,750.00

e Kawat beton 4.00 kg 15,000.00 60,000.00

Page 23: 166742630 Analisa Harga Satuan Pekerjaan Medan

f Semen PC (abu-abu) 6.45 sak 49,500.00 319,275.00

g Pasir beton 0.52 m

3 140,000.00 72,800.00

h Split (batu pecah) 0.78 m

3 140,000.00 109,200.00

i Balok kayu Borneo Super 0.14 m

3 4,000,000.00 560,000.00

j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00

k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,000.00 128,000.00

l Pembantu tukang 5.96 org 50,000.00 298,000.00

m Tukang batu 0.35 org 87,500.00 30,625.00

n Tukang kayu 2.80 org 87,500.00 245,000.00

o Tukang besi 1.40 org 87,500.00 122,500.00

Jumlah 4,884,810.00

Dibulatkan 4,884,800.00

13 1 M

3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m

3 1,448,200.00 463,424.00

b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00

c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00

d Besi beton polos 250.00 kg 13,950.00 3,487,500.00

e Kawat beton 6.00 kg 13,400.00 80,400.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.14 m

3 5,400,000.00 756,000.00

j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00

k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,000.00 128,000.00

l Pembantu tukang 5.96 org 50,000.00 298,000.00

m Tukang batu 0.35 org 87,500.00 30,625.00

n Tukang kayu 2.80 org 87,500.00 245,000.00

o Tukang besi 1.40 org 87,500.00 122,500.00

Jumlah 6,632,849.00

Dibulatkan 6,632,800.00

Page 24: 166742630 Analisa Harga Satuan Pekerjaan Medan

14 1 M

3 MEMBUAT TANGGA BETON BERTULANG ( 200 kg BESI + BEKISTING )

a Papan kayu terentang 0.25 m

3 1,448,200.00 362,050.00

b Paku 5 - 12 cm 3.00 kg 17,500.00 52,500.00

c Pelumas begisting (oli/minyak) 1.20 Ltr 12,500.00 15,000.00

d Besi beton polos 200.00 kg 13,950.00 2,790,000.00

e Kawat beton 3.00 kg 13,400.00 40,200.00

f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Balok kayu Borneo Super 0.30 m

3 5,400,000.00 1,620,000.00

j Multiplex 120 x 240 x 9 mm 2.50 lbr 120,950.00 302,375.00

k Pembantu tukang 5.60 org 50,000.00 280,000.00

l Tukang batu 0.35 org 87,500.00 30,625.00

m Tukang kayu 2.30 org 87,500.00 201,250.00

n Tukang besi 1.40 org 87,500.00 122,500.00

Jumlah 6,423,240.00

Dibulatkan 6,423,200.00

15 1 M

3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m

3 761,800.00 761,800.00

b Pasang Bekisting untuk lantai 10.00 m

2 370,600.00 3,706,000.00

c Besi Beton rakit 100.00 kg 13,950.00 1,395,000.00

Jumlah 5,862,800.00

Dibulatkan 5,862,800.00

16 1 M

3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m

3 761,800.00 761,800.00

b Pasang Bekisting untuk lantai 8.33 m

2 370,600.00 3,087,098.00

c Besi Beton rakit 115.00 kg 16,200.00 1,863,000.00

Jumlah 5,711,898.00

Dibulatkan 5,711,800.00

17 1 M

3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )

Page 25: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m

3 761,800.00 761,800.00

b Pasang Bekisting untuk lantai 8.33 m

2 370,600.00 3,087,098.00

c Besi Beton rakit 125.00 kg 16,200.00 2,025,000.00

Jumlah 5,873,898.00

Dibulatkan 5,873,800.00

18 1 M

3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m

3 761,800.00 761,800.00

b Pasang Bekisting untuk lantai 6.67 m2 370,600.00 2,471,902.00

c Besi Beton rakit 100.00 kg 16,200.00 1,620,000.00

Jumlah 4,853,702.00

Dibulatkan 4,853,700.00

19 1 M

3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m

3 761,800.00 761,800.00

b Pasang Bekisting untuk lantai 7.50 m

2 370,600.00 2,779,500.00

c Besi Beton rakit 115.00 kg 16,200.00 1,863,000.00

Jumlah 5,404,300.00

Dibulatkan 5,404,300.00

20 1M

3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225

a Papan kayu terentang 0.27 m

3 1,448,200.00 391,014.00

b Paku 5 - 12 cm 2.00 kg 17,500.00 35,000.00

c Pelumas begisting (oli/minyak) 0.60 Ltr 12,500.00 7,500.00

d Besi beton polos 175.00 kg 13,950.00 2,441,250.00

e Kawat beton 3.00 kg 13,400.00 40,200.00

f Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00

g Pasir beton 0.52 m

3 92,000.00 47,840.00

h Split (batu pecah) 0.78 m

3 270,000.00 210,600.00

i Pembantu tukang 4.85 org 50,000.00 242,500.00

j Tukang batu 0.40 org 87,500.00 35,000.00

k Tukang kayu 1.75 org 87,500.00 153,125.00

l Tukang besi 1.45 org 87,500.00 126,875.00

Page 26: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 4,162,904.00

Dibulatkan 4,162,900.00

V PEKERJAAN DINDING

1 1 M

2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps

a Bata merah 140.00 bh 650.00 91,000.00

b Semen PC (abu-abu) 0.65 sak 54,000.00 35,100.00

c Pasir pasang 0.09 m

3 84,000.00 7,560.00

d Pembantu tukang 0.65 org 50,000.00 32,500.00

e Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 183,660.00

Dibulatkan 183,600.00

2 1 M

2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps

a Bata merah 140.00 bh 650.00 91,000.00

b Semen PC (abu-abu) 0.55 sak 54,000.00 29,700.00

c Pasir pasang 0.09 m

3 84,000.00 7,560.00

d Pembantu tukang 0.65 org 50,000.00 32,500.00

e Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 178,260.00

Dibulatkan 178,200.00

3 1 M

2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps

a Bata merah 140.00 bh 650.00 91,000.00

b Semen PC (abu-abu) 0.45 sak 54,000.00 24,300.00

c Pasir pasang 0.10 m

3 84,000.00 8,400.00

d Pembantu tukang 0.65 org 50,000.00 32,500.00

e Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 173,700.00

Dibulatkan 173,700.00

4 1 M

2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps

Page 27: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Bata merah 70.00 bh 650.00 45,500.00

b Semen PC (abu-abu) 0.29 sak 54,000.00 15,660.00

c Pasir pasang 0.04 m

3 84,000.00 3,360.00

d Pembantu tukang 0.32 org 50,000.00 16,000.00

e Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 89,270.00

Dibulatkan 89,200.00

5 1 M

2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps

a Bata merah 70.00 bh 650.00 45,500.00

b Semen PC (abu-abu) 0.25 sak 54,000.00 13,500.00

c Pasir pasang 0.05 m

3 84,000.00 4,200.00

d Pembantu tukang 0.32 org 50,000.00 16,000.00

e Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 87,950.00

Dibulatkan 87,900.00

6 1 M

2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps

a Bata merah 70.00 bh 650.00 45,500.00

b Semen PC (abu-abu) 0.22 sak 54,000.00 11,880.00

c Pasir pasang 0.05 m

3 84,000.00 4,200.00

d Pembantu tukang 0.32 org 50,000.00 16,000.00

e Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 86,330.00

Dibulatkan 86,300.00

7 1 M

2 PASANG DINDING BATA ROOSTER / BATA TERAWANG

a Rooster / Terawang ukuran 12 x 11 x 24 37.00 bh 4,200.00 155,400.00

b Semen PC (abu-abu) 0.27 sak 54,000.00 14,580.00

c Pasir pasang 0.04 m

3 84,000.00 3,360.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 197,090.00

Page 28: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 197,000.00

8 1 M

2 PASANG DINDING GLASSBLOCK

a Glassblock ukuran 18 x 18 cm 30.00 bh 21,500.00 645,000.00

b Semen putih 0.27 sak 12,700.00 3,429.00

c Pembantu tukang 0.30 org 50,000.00 15,000.00

d Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 672,179.00

Dibulatkan 672,100.00

9 1 M

2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps

a Bataco putih 15.00 bh 4,000.00 60,000.00

b Semen PC (abu-abu) 0.25 sak 54,000.00 13,500.00

c Pasir pasang 0.03 m

3 84,000.00 2,520.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 104,145.00

Dibulatkan 104,100.00

10 1 M

2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps

a Bataco press semen 15.00 bh 4,200.00 63,000.00

b Semen PC (abu-abu) 0.20 sak 54,000.00 10,800.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 103,605.00

Dibulatkan 103,600.00

11 1 M

2 PASANGAN BATA RINGAN ( HEBEL/CELCON ).

a Bata Ringan ( hebel/celcon ) 8.00 bh 3,500.00 28,000.00

b Semen Instan 11.45 kg 2,450.00 28,052.50

c Pembantu tukang 0.30 org 50,000.00 15,000.00

d Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 88,552.50

Page 29: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 88,500.00

VI PEKERJAAN PLESTERAN/ACCI

1 1 M

2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.14 sak 54,000.00 7,560.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 32,365.00

Dibulatkan 32,300.00

2 1 M

2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.13 sak 54,000.00 7,020.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 31,825.00

Dibulatkan 31,800.00

3 1 M

2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.10 sak 54,000.00 5,400.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 30,205.00

Dibulatkan 30,200.00

4 1 M

2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.09 sak 54,000.00 4,860.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang batu 0.15 org 87,500.00 13,125.00

Page 30: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 29,665.00

Dibulatkan 29,600.00

5 1 M

2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm

a Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00

b Pasir pasang 0.03 m

3 84,000.00 2,520.00

c Pembantu tukang 0.22 org 50,000.00 11,000.00

d Tukang batu 0.16 org 87,500.00 14,000.00

Jumlah 36,700.00

Dibulatkan 36,700.00

6 1 M

2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm

a Semen PC (abu-abu) 0.15 sak 54,000.00 8,100.00

b Pasir pasang 0.03 m

3 84,000.00 2,520.00

c Pembantu tukang 0.25 org 50,000.00 12,500.00

d Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 40,620.00

Dibulatkan 40,600.00

7 1 M

2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.11 sak 54,000.00 5,940.00

b Pasir pasang 0.03 m

3 84,000.00 2,100.00

c Pembantu tukang 0.15 org 50,000.00 7,500.00

d Tukang batu 0.07 org 87,500.00 6,125.00

Jumlah 21,665.00

Dibulatkan 21,600.00

8 1 M

2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.19 sak 54,000.00 10,260.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.26 org 50,000.00 13,000.00

d Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 42,440.00

Dibulatkan 42,400.00

Page 31: 166742630 Analisa Harga Satuan Pekerjaan Medan

9 1 M

2 PLESTERAN BETON CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.15 sak 54,000.00 8,100.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.26 org 50,000.00 13,000.00

d Tukang batu 0.20 org 87,500.00 17,500.00

Jumlah 40,280.00

Dibulatkan 40,200.00

10 1 M

2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps

a Semen PC (abu-abu) 0.01 sak 54,000.00 540.00

b Pasir pasang 0.01 m

3 84,000.00 840.00

c Pembantu tukang 0.06 org 50,000.00 3,000.00

d Tukang batu 0.04 org 87,500.00 3,500.00

Jumlah 7,880.00

Dibulatkan 7,800.00

11 1 M

2 ACCIAN PLESTERAN

a Semen PC (abu-abu) 0.08 sak 54,000.00 4,320.00

b Pembantu tukang 0.14 org 50,000.00 7,000.00

c Tukang batu 0.11 org 87,500.00 9,625.00

Jumlah 20,945.00

Dibulatkan 20,900.00

12 1 M

2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps

a Semen PC (abu-abu) 0.09 sak 54,000.00 4,860.00

b Pasir pasang 0.02 m

3 84,000.00 1,680.00

c Pembantu tukang 0.15 org 50,000.00 7,500.00

d Tukang batu 0.07 org 87,500.00 6,125.00

Jumlah 20,165.00

Dibulatkan 20,100.00

VII PEKERJAAN PELAPIS LANTAI

Page 32: 166742630 Analisa Harga Satuan Pekerjaan Medan

1 1 M

2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm POLISHED

a Keramik ukuran 40 x 40 cm 1.00 m

2 225,000.00 225,000.00

b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,806.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.25 org 50,000.00 12,500.00

f Tukang batu 0.12 org 87,500.00 10,500.00

Jumlah 258,700.00

Dibulatkan 258,700.00

2 1 M

2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH

a Keramik ukuran 40 x 40 cm 1.00 m

2 202,000.00 202,000.00

b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.26 org 50,000.00 13,000.00

f Tukang batu 0.13 org 87,500.00 10,937.50

Jumlah 236,511.50

Dibulatkan 236,510.00

3 1 M

2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm

a Keramik ukuran 60 x 60 cm 1.00 m

2 298,000.00 298,000.00

b Semen PC (abu-abu) 0.18 sak 54,000.00 9,720.00

c Pasir pasang 0.02 m

3 84,000.00 1,806.00

d Semen warna 0.01 kg 12,700.00 165.10

e Pembantu tukang 0.25 org 50,000.00 12,500.00

f Tukang batu 0.12 org 87,500.00 10,500.00

Jumlah 332,691.10

Dibulatkan 332,690.00

4 1 M

2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm

a Keramik ukuran 60 x 90 cm 1.00 m

2 340,000.00 340,000.00

b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00

Page 33: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Pasir pasang 0.02 m

3 84,000.00 1,806.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.26 org 50,000.00 13,000.00

f Tukang batu 0.14 org 87,500.00 12,250.00

Jumlah 376,490.00

Dibulatkan 376,490.00

5 1 M

2 PASANG LANTAI KERAMIK 10 x 20 cm

a Keramik lantai 10 x 20 cm 1.00 m

2 34,000.00 34,000.00

b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.22 org 50,000.00 11,000.00

f Tukang batu 0.40 org 87,500.00 35,000.00

Jumlah 91,654.00

Dibulatkan 91,650.00

6 1 M

2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm

a Keramik polos 20 x 20 cm 1.00 m

2 37,000.00 37,000.00

b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00

c Pasir pasang 0.02 m

3 84,000.00 1,806.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.30 org 50,000.00 15,000.00

f Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 76,365.00

Dibulatkan 76,360.00

7 1 M

2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm

a Keramik motif 20 x 20 cm 1.00 m

2 39,000.00 39,000.00

b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00

c Pasir pasang 0.02 m

3 84,000.00 1,806.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.30 org 50,000.00 15,000.00

Page 34: 166742630 Analisa Harga Satuan Pekerjaan Medan

f Tukang batu 0.15 org 87,500.00 13,125.00

Jumlah 78,365.00

Dibulatkan 78,360.00

8 1 M

2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm

a Keramik polos 30 x 30 cm 1.00 m

2 39,000.00 39,000.00

b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.25 org 50,000.00 12,500.00

f Tukang batu 0.12 org 87,500.00 10,500.00

Jumlah 72,574.00

Dibulatkan 72,570.00

9 1 M

2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm

a Keramik motif 30 x 30 cm 1.00 m

2 43,000.00 43,000.00

b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.25 org 50,000.00 12,500.00

f Tukang batu 0.12 org 87,500.00 10,500.00

Jumlah 76,574.00

Dibulatkan 76,570.00

10 1 M

2 PASANG LANTAI MARMER

a marmer standar 1.00 m

2 212,000.00 212,000.00

b Semen PC (abu-abu) 0.48 sak 54,000.00 25,920.00

c Pasir pasang 0.10 m

3 84,000.00 8,400.00

d Semen warna 0.20 sak 12,700.00 2,540.00

e Pembantu tukang 0.62 org 50,000.00 31,000.00

f Tukang batu 0.35 org 87,500.00 30,625.00

Jumlah 310,485.00

Dibulatkan 310,480.00

Page 35: 166742630 Analisa Harga Satuan Pekerjaan Medan

11 1 M

2 PASANG LANTAI PARQUET JATI

a Parquet jati 1.05 m

2 276,000.00 289,800.00

b Lem vinyl 0.60 kg 32,000.00 19,200.00

c Pembantu tukang 0.65 org 50,000.00 32,500.00

d Tukang 0.35 org 87,500.00 30,625.00

Jumlah 372,125.00

Dibulatkan 372,120.00

12 1 M

2 PASANG LANTAI GRANIT

a Granit standar 1.00 m

2 750,000.00 750,000.00

b Semen PC (abu-abu) 0.48 sak 54,000.00 25,920.00

c Pasir pasang 0.08 m

3 84,000.00 6,720.00

d Semen warna 0.10 sak 12,700.00 1,270.00

e Pembantu tukang 0.60 org 50,000.00 30,000.00

f Tukang batu 0.48 org 87,500.00 42,000.00

Jumlah 855,910.00

Dibulatkan 855,910.00

VIII PEKERJAAN PELAPIS DINDING

1 1 M

2 PASANG DINDING KERAMIK MOTIF 10 x 20 cm

a Keramik motif 10 x 20 cm 1.00 m

2 38,000.00 38,000.00

b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.22 org 50,000.00 11,000.00

f Tukang batu 0.40 org 87,500.00 35,000.00

Jumlah 95,654.00

Dibulatkan 95,650.00

2 1 M

2 PASANG DINDING KERAMIK POLOS 10 x 20 cm

Page 36: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Keramik polos 10 x 20 cm 1.00 m

2 36,000.00 36,000.00

b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.22 org 50,000.00 11,000.00

f Tukang batu 0.40 org 87,500.00 35,000.00

Jumlah 93,654.00

Dibulatkan 93,650.00

3 1 M

2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm

a Keramik motif 20 x 20 cm 1.00 m

2 39,000.00 39,000.00

b Semen PC ( abu-abu ) 0.17 sak 54,000.00 9,180.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.20 org 50,000.00 10,000.00

f Tukang batu 0.39 org 87,500.00 34,125.00

Jumlah 94,239.00

Dibulatkan 94,230.00

4 1 M

2 PASANG DINDING KERAMIK POLOS 20 x 20 cm

a Keramik polos 20 x 20 cm 1.00 m

2 37,000.00 37,000.00

b Semen PC ( abu-abu ) 0.17 sak 54,000.00 9,180.00

c Pasir pasang 0.02 m

3 84,000.00 1,680.00

d Semen warna 0.02 kg 12,700.00 254.00

e Pembantu tukang 0.20 org 50,000.00 10,000.00

f Tukang batu 0.39 org 87,500.00 34,125.00

Jumlah 92,239.00

Dibulatkan 92,230.00

5 1 M

2 PASANG DINDING KERAMIK POLOS 20 x 25 cm

a Keramik polos 20 x 25 cm 1.00 m

2 38,000.00 38,000.00

b Semen PC ( abu-abu ) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,512.00

Page 37: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Semen warna 0.01 kg 12,700.00 165.10

e Pembantu tukang 0.19 org 50,000.00 9,375.00

f Tukang batu 0.38 org 87,500.00 32,812.50

Jumlah 90,504.60

Dibulatkan 90,500.00

6 1 M

2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm

a Keramik motif 20 x 25 cm 1.00 m

2 39,000.00 39,000.00

b Semen PC ( abu-abu ) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.02 m

3 84,000.00 1,512.00

d Semen warna 0.01 kg 12,700.00 165.10

e Pembantu tukang 0.19 org 50,000.00 9,375.00

f Tukang batu 0.38 org 87,500.00 32,812.50

Jumlah 91,504.60

Dibulatkan 91,500.00

7 1 M

2 PASANG DINDING MARMER

a Marmer standar 1.00 m

2 212,000.00 212,000.00

b Paku sekrup 4.00 bh 600.00 2,400.00

c Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00

d Pasir pasang 0.03 m

3 84,000.00 2,100.00

e Semen warna 1.50 kg 12,700.00 19,050.00

f Kawat ikat 0.03 kg 13,400.00 335.00

g Paku 0.03 kg 17,500.00 437.50

h Pembantu tukang 0.72 org 50,000.00 36,000.00

i Tukang batu 0.65 org 87,500.00 56,875.00

Jumlah 342,697.50

Dibulatkan 342,690.00

8 1 M

2 PASANG DINDING GRANIT

a Granit standar 1.00 m

2 750,000.00 750,000.00

b Paku sekrup 2.00 bh 600.00 1,200.00

c Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00

Page 38: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Pasir pasang 0.03 m

3 84,000.00 2,100.00

e Semen warna 1.50 kg 12,700.00 19,050.00

f Kawat ikat 0.03 kg 13,400.00 335.00

g Paku 0.03 kg 17,500.00 437.50

h Pembantu tukang 0.72 org 50,000.00 36,000.00

i Tukang batu 0.65 org 87,500.00 56,875.00

Jumlah 879,497.50

Dibulatkan 879,490.00

9 1 M

2 PASANG DINDING BATU TEMPEL HITAM

a Batu tempel hitam 1.00 m

2 108,200.00 108,200.00

b Semen PC ( abu-abu ) 0.24 sak 54,000.00 12,960.00

c Pasir pasang 0.04 m

3 84,000.00 2,940.00

d Pembantu tukang 0.32 org 50,000.00 16,000.00

e Tukang batu 0.25 org 87,500.00 21,875.00

Jumlah 161,975.00

Dibulatkan 161,970.00

10 1 M

2 PASANG DINDING BATU ALAM

a Batu alam 1.00 m

2 157,900.00 157,900.00

b Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00

c Pasir pasang 0.04 m

3 84,000.00 2,940.00

d Pembantu tukang 0.32 org 50,000.00 16,000.00

e Tukang batu 0.25 org 87,500.00 21,875.00

Jumlah 212,215.00

Dibulatkan 212,210.00

11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm

a Plint Keramik ukuran 10 x 40 cm 2.65 bh 10,000.00 26,500.00

b Semen PC (abu-abu) 0.02 sak 54,000.00 1,080.00

c Pasir pasang 0.01 m

3 84,000.00 840.00

d Semen warna 0.10 kg 12,700.00 1,270.00

e Pembantu tukang 0.06 org 50,000.00 3,000.00

Page 39: 166742630 Analisa Harga Satuan Pekerjaan Medan

f Tukang batu 0.03 org 87,500.00 2,625.00

Jumlah 35,315.00

Dibulatkan 35,310.00

12 1 m¹ PASANG PLINT KERAMIK UKURAN 10 x 30 cm

a Plint Keramik ukuran 10 x 30 cm 3.30 bh 8,000.00 26,400.00

b Semen PC (abu-abu) 0.02 sak 54,000.00 1,080.00

c Pasir pasang 0.01 m

3 84,000.00 840.00

d Semen warna 0.12 kg 12,700.00 1,524.00

e Pembantu tukang 0.06 org 50,000.00 3,000.00

f Tukang batu 0.03 org 87,500.00 2,625.00

Jumlah 35,469.00

Dibulatkan 35,460.00

IX PEKERJAAN KUSEN, PINTU, JENDELA, PARTISI

1 1 M

3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER SAMARINDA

a Balok kayu kamper samarinda 1.20 m

3 9,670,000.00 11,604,000.00

b Pembantu tukang 6.00 org 50,000.00 300,000.00

c Tukang kayu 15.00 org 87,500.00 1,312,500.00

Jumlah 13,216,500.00

Dibulatkan 13,216,500.00

2 1 M

3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER MEDAN / KRUING

a Balok kayu kamper medan 1.20 m

3 6,550,000.00 7,860,000.00

b Pembantu tukang 6.00 org 50,000.00 300,000.00

c Tukang kayu 15.00 org 87,500.00 1,312,500.00

Jumlah 9,472,500.00

Dibulatkan 9,472,500.00

3 1 M

3 PASANG KUSEN PINTU & JENDELA KAYU BORNEO SUPER

a Kayu balok borneo super 1.20 m

3 5,400,000.00 6,480,000.00

Page 40: 166742630 Analisa Harga Satuan Pekerjaan Medan

b Pembantu tukang 6.00 org 50,000.00 300,000.00

c Tukang kayu 15.00 org 87,500.00 1,312,500.00

Jumlah 8,092,500.00

Dibulatkan 8,092,500.00

4 1 M

2 PASANG PINTU PANEL KAYU KAMPER SAMARINDA

a Papan kayu kamper samarinda 0.04 m

3 9,980,000.00 399,200.00

b Pembantu tukang 1.00 org 50,000.00 50,000.00

c Tukang kayu 2.50 org 87,500.00 218,750.00

Jumlah 667,950.00

Dibulatkan 667,950.00

5 1 M

2 PASANG PINTU PANEL KAYU KAMPER MEDAN / KRUING

a Papan kayu kamper medan 0.04 m

3 6,750,000.00 270,000.00

b Pembantu tukang 1.00 org 50,000.00 50,000.00

c Tukang kayu 2.50 org 87,500.00 218,750.00

Jumlah 538,750.00

Dibulatkan 538,750.00

6 1 M

2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER MEDAN

a Papan kayu kamper medan 0.04 m

3 6,750,000.00 245,000.00

b Pembantu tukang 0.80 org 50,000.00 91,875.00

c Tukang kayu 2.00 org 87,500.00 245,000.00

Jumlah 581,875.00

Dibulatkan 581,800.00

7 1 M

2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO

a Papan kayu borneo super 0.04 m

3 5,660,000.00 56,000.00

b Pembantu tukang 0.80 org 50,000.00 20,000.00

c Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 251,000.00

Dibulatkan 251,000.00

8 1 M

2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER MEDAN

a Papan kayu Kamper Medan 0.06 m

3 6,750,000.00 432,000.00

Page 41: 166742630 Analisa Harga Satuan Pekerjaan Medan

b Pembantu tukang 1.00 org 50,000.00 50,000.00

c Tukang kayu 3.00 org 87,500.00 262,500.00

Jumlah 744,500.00

Dibulatkan 744,500.00

9 1 M

2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU KAMPER MEDAN

a Papan kayu kamper medan 0.02 m

3 6,750,000.00 132,300.00

b Paku 1 s/d 5 cm 0.03 kg 17,500.00 525.00

c Lem Kayu 0.30 Ltr 27,000.00 8,100.00

d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00

e Pembantu tukang 0.60 org 50,000.00 30,000.00

f Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 387,925.00

Dibulatkan 387,900.00

10 1 M

2 PASANG JALUSI MATI KUSEN KAYU KAMPER MEDAN

a Papan kayu kamper medan 0.06 m

3 6,750,000.00 405,000.00

b Paku 1 s/d 5 cm 0.15 kg 17,500.00 2,625.00

c Pembantu tukang 0.50 org 50,000.00 25,000.00

d Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 607,625.00

Dibulatkan 607,600.00

11 1 M

2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU BORNEO SUPER

a Papan kayu borneo super 0.02 m

3 5,660,000.00 110,936.00

b Paku 1 s/d 5 cm 0.03 kg 17,500.00 525.00

c Lem kayu 0.30 Ltr 27,000.00 8,100.00

d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00

e Pembantu tukang 0.60 org 50,000.00 30,000.00

f Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 366,561.00

Dibulatkan 366,500.00

12 1 M

2 PASANG PINTU TEAKWOOD RANGKAP , RANGKA KAYU KAMPER MEDAN

Page 42: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Papan kayu Kamper Medan 0.02 m

3 6,750,000.00 132,300.00

b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00

c Lem Kayu 0.30 Ltr 27,000.00 8,100.00

d Teakwood 120 x 240 x 0,4 cm 1.00 lbr 82,000.00 82,000.00

e Pembantu tukang 0.60 org 50,000.00 30,000.00

f Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 432,650.00

Dibulatkan 432,600.00

13 1 M

2 PASANG PINTU TRIPLEK & FORMIKA RANGKA KAYU KAMPER MEDAN

a Papan kayu kamper medan 0.02 m

3 6,750,000.00 132,300.00

b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00

c Lem kayu 0.80 Ltr 27,000.00 21,600.00

d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00

e Formica 3" x 6" 0.50 lbr 166,700.00 83,350.00

f Pembantu tukang 0.80 org 50,000.00 40,000.00

g Tukang kayu 2.50 org 87,500.00 218,750.00

Jumlah 543,250.00

Dibulatkan 543,200.00

14 1 M

2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU KAMPER MEDAN

a Papan kayu kamper medan 0.02 m

3 6,750,000.00 132,300.00

b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00

c Lem Kayu 0.80 Ltr 27,000.00 21,600.00

d Teakwood 120 x 240 x 0,4 cm 0.50 lbr 82,000.00 41,000.00

e Vernis 0.50 Ltr 50,000.00 25,000.00

a Formica 4" x 8" 0.50 lbr 166,700.00 83,350.00

b Pembantu tukang 0.80 org 50,000.00 40,000.00

c Tukang kayu 2.50 org 87,500.00 218,750.00

Jumlah 567,250.00

Dibulatkan 567,200.00

15 1 M

2 PASANG DINDING PEMISAH DOUBLE TEAKWOOD, RANGKA KAYU KAMPER MEDAN

Page 43: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Balok kayu Kamper Medan 0.02 m

3 6,550,000.00 127,725.00

b Papan kayu Kamper Medan 0.01 m

3 6,750,000.00 47,250.00

c Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00

d Lem Kayu 0.56 Ltr 27,000.00 15,120.00

e Teakwood 120 x 240 x 0,4 cm 1.00 lbr 82,000.00 82,000.00

f Pembantu tukang 0.15 org 50,000.00 7,500.00

g Tukang kayu 0.45 org 87,500.00 39,375.00

Jumlah 320,720.00

Dibulatkan 320,700.00

16 1 M

2 PASANG DINDING PEMISAH DOUBLE GRC, RANGKA KAYU KAMPER MEDAN

a Balok kayu Kamper Medan 0.02 m

3 6,550,000.00 127,725.00

b Papan kayu Kamper Medan 0.01 m

3 6,750,000.00 47,250.00

c Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00

d Lem Kayu 0.56 Ltr 27,000.00 15,120.00

e Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00

f Pembantu tukang 0.20 org 50,000.00 10,000.00

g Tukang kayu 0.60 org 87,500.00 52,500.00

Jumlah 296,345.00

Dibulatkan 296,300.00

17 1 BH PASANG PINTU ALUMINIUM / PINTU PVC

a Pintu Aluminium / Pintu PVC 1.00 bh 400,000.00 400,000.00

b Alat bantu 10 % harga material 1.00 ls 40,000.00 40,000.00

c Tukang kayu 0.02 org 87,500.00 1,837.50

Jumlah 441,837.50

Dibulatkan 441,800.00

18 1 M

2 PASANG KUSEN PARTISI DOUBLE TRIPLEK

a Balok kayu borneo super 0.11 m

3 5,400,000.00 567,000.00

b Triplek 0,4 cm ukuran pintu 5.00 lbr 42,000.00 210,000.00

c Paku 1 s/d 3 cm 2.00 kg 17,500.00 35,000.00

d Ampelas 2.00 lbr 2,500.00 5,000.00

Page 44: 166742630 Analisa Harga Satuan Pekerjaan Medan

e Engsel 4.00 bh 25,000.00 100,000.00

f Grendel / slot 4.00 bh 33,000.00 132,000.00

g Pembantu tukang 0.30 org 50,000.00 15,000.00

h Tukang kayu terampil 1.30 org 87,500.00 113,750.00

Jumlah 1,177,750.00

Dibulatkan 129,530.00

19 1 M

2 PASANG KUSEN PARTISI DOUBLE GYPSUM + RANGKA KAYU

a Balok kayu borneo super 0.11 m

3 5,400,000.00 567,000.00

b Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 86,000.00 61,920.00

c Paku 1 s/d 3 cm 2.00 kg 17,500.00 35,000.00

d Ampelas 2.00 lbr 2,500.00 5,000.00

e Engsel 4.00 bh 25,000.00 100,000.00

f Grendel / Slot 4.00 bh 33,000.00 132,000.00

g Pembantu tukang 0.30 org 50,000.00 15,000.00

h Tukang kayu 1.30 org 87,500.00 113,750.00

Jumlah 1,029,670.00

Dibulatkan 129,530.00

20 1 M

2 PASANG DINDING PARTISI GYPSUM BOARD + RANGKA BESI HOLLOW

a Hollow 4/4 Zincromate 0.42 btg 48,000.00 20,160.00

b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00

c Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 86,000.00 61,920.00

d Paku sekrup 25.00 bh 600.00 15,000.00

e Ramset / dina bolt 4.00 bh 2,800.00 11,200.00

f Cotton plaster 0.10 bh 55,500.00 5,550.00

g Compoun 0.13 kg 30,000.00 3,900.00

h Pembantu tukang 0.10 org 50,000.00 5,000.00

i Tukang kayu 0.05 org 87,500.00 4,375.00

Jumlah 132,355.00

Dibulatkan 132,350.00

Page 45: 166742630 Analisa Harga Satuan Pekerjaan Medan

X PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP

A PEKERJAAN RANGKA ATAP

1 1 M

3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU KAMPER MEDAN

a Balok kayu kamper medan 1.10 m

3 6,550,000.00 7,205,000.00

b Besi strip 15.00 kg 14,100.00 211,500.00

c Paku ukuran besar 0.80 kg 17,500.00 14,000.00

d Meni kayu 0.40 kg 17,000.00 6,800.00

e Pembantu tukang 4.00 org 50,000.00 200,000.00

f Tukang kayu 12.00 org 87,500.00 1,050,000.00

Jumlah 8,687,300.00

Dibulatkan 8,687,300.00

2 1 M

3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU BORNEO SUPER

a Balok kayu borneo super 1.10 m

3 5,400,000.00 5,940,000.00

b Besi strip 15.00 kg 14,100.00 211,500.00

c Paku ukuran besar 0.80 kg 17,500.00 14,000.00

d Meni kayu 0.40 kg 17,000.00 6,800.00

e Pembantu tukang 4.00 org 50,000.00 200,000.00

f Tukang kayu 12.00 org 87,500.00 1,050,000.00

Jumlah 7,422,300.00

Dibulatkan 7,422,300.00

3 1 M

2 PASANG KASO + RENG GENTENG PLENTONG KAYU BORNEO SUPER

a Balok kayu borneo super 0.01 m

3 5,400,000.00 64,800.00

b Paku 7 - 10 cm 0.15 kg 17,500.00 2,625.00

c Pembantu tukang 0.10 org 50,000.00 5,000.00

d Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 81,175.00

Dibulatkan 81,100.00

Page 46: 166742630 Analisa Harga Satuan Pekerjaan Medan

4 1 M

2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO SUPER

a Balok kayu borneo super 0.01 m

3 5,400,000.00 75,600.00

b Paku 7 - 10 cm 0.15 kg 17,500.00 2,625.00

c Pembantu tukang 0.10 org 50,000.00 5,000.00

d Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 91,975.00

Dibulatkan 91,900.00

5 1 M

1 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 20 cm

a Papan kayu kamper medan 0.01 m

3 6,750,000.00 48,600.00

b Paku 7 - 10 cm 0.05 kg 17,500.00 875.00

c Pembantu tukang 0.10 org 50,000.00 5,000.00

d Tukang kayu 0.20 org 87,500.00 17,500.00

Jumlah 71,975.00

Dibulatkan 71,900.00

6 1 M

2 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 30 cm

a Papan kayu kamper medan 0.01 m

3 6,750,000.00 74,250.00

b Paku 7 - 10 cm 0.05 kg 17,500.00 875.00

c Pembantu tukang 0.11 org 50,000.00 5,500.00

d Tukang kayu 0.22 org 87,500.00 19,250.00

Jumlah 99,875.00

Dibulatkan 99,800.00

7 1 M

3 PEKERJAAN NOK/GORDING/JURAY KAYU BORNEO SUPER

a Balok kayu borneo super 1.05 m

3 5,400,000.00 5,670,000.00

b Paku 10 - 15 cm 0.20 kg 17,500.00 3,500.00

c Pembantu tukang 2.00 org 50,000.00 100,000.00

d Tukang kayu 2.00 org 87,500.00 175,000.00

Jumlah 5,948,500.00

Dibulatkan 5,948,500.00

B PEKERJAAN PENUTUP ATAP

1 1 M

2 PASANG ATAP GENTENG PLENTONG

Page 47: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Genteng palentong 25.00 bh 800.00 20,000.00

b Pembantu tukang 0.15 org 50,000.00 7,500.00

c Tukang kayu 0.08 org 87,500.00 6,562.50

Jumlah 34,062.50

Dibulatkan 34,060.00

2 1 M

2 PASANG NOK/BUBUNGAN GENTENG KERAMIK GLAZUR

a Genteng nok/bubungan plentong 5.00 bh 24,000.00 120,000.00

b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00

c Pasir pasang 0.03 m

3 84,000.00 2,688.00

d Pembantu tukang 0.30 org 50,000.00 15,000.00

e Tukang kayu 0.20 org 87,500.00 17,500.00

Jumlah 163,828.00

Dibulatkan 163,820.00

3 1 M

2 PASANG ATAP FIBREGLASS UKURAN 180 X 90 cm

a Atap fibreglass 0.60 lbr 72,500.00 43,500.00

b Paku 2 - 5 cm 0.05 kg 17,500.00 875.00

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 5,862.50

Jumlah 57,237.50

Dibulatkan 57,230.00

4 1 M

2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,05 m TEBAL 4 mm

a Asbes gelombang 0.35 lbr 70,000.00 24,500.00

b Paku payung 0.12 kg 17,500.00 2,100.00

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 39,725.00

Dibulatkan 39,720.00

5 1 M

2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,05 m TEBAL 4 mm

a Asbes gelombang 0.42 lbr 62,000.00 26,040.00

b Paku payung 0.12 kg 17,500.00 2,100.00

Page 48: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 41,265.00

Dibulatkan 41,260.00

6 1 M

2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,02 m TEBAL 5 mm

a Asbes gelombang 0.44 lbr 92,000.00 40,480.00

b Paku payung 0.12 kg 17,500.00 2,100.00

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 5,862.50

Jumlah 55,442.50

Dibulatkan 55,440.00

7 1 M

2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,02 m TEBAL 5 mm

a Asbes gelombang 0.51 lbr 84,000.00 42,840.00

b Paku payung 0.12 kg 17,500.00 2,100.00

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 5,862.50

Jumlah 57,802.50

Dibulatkan 57,800.00

8 1 M

2 PASANG ATAP ASBES GELOMBANG ( 1,50 x 1,02 m ) x 5 mm

a Asbes gelombang 0.80 lbr 48,000.00 38,400.00

b Paku payung 0.12 kg 17,500.00 2,100.00

c Pembantu tukang 0.14 org 50,000.00 7,000.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 53,625.00

Dibulatkan 53,620.00

9 1 M¹ PASANG ATAP SIRAP

a Genteng sirap 80.00 bh 1,100.00 88,000.00

b Paku 0.20 kg 17,500.00 3,500.00

c Pembantu tukang 0.10 org 50,000.00 5,000.00

d Tukang kayu 0.20 org 87,500.00 17,500.00

Page 49: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 114,000.00

Dibulatkan 114,000.00

10 1 M

2 PASANG ATAP GENTENG BETON

a Genteng beton 1.10 bh 70,000.00 77,000.00

b Paku 5 - 12 cm 0.03 kg 17,500.00 525.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 96,275.00

Dibulatkan 96,270.00

11 1 M

2 PASANG ATAP GENTENG METAL + C301

a Genteng metal 1.02 lbr 134,000.00 136,680.00

b Paku 5 - 12 cm 0.20 kg 17,500.00 3,500.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 158,930.00

Dibulatkan 158,930.00

12 1 M¹ PASANG NOK GENTENG BETON

a Nok genteng beton 3.50 bh 15,000.00 52,500.00

b Paku 5 - 12 cm 0.05 kg 17,500.00 875.00

c Semen PC (abu-abu) 0.22 sak 54,000.00 11,664.00

d Pasir pasang 0.03 m

3 84,000.00 2,688.00

e Semen warna 1.00 kg 12,700.00 12,700.00

f Pembantu tukang 0.40 org 50,000.00 20,000.00

g Tukang kayu 0.20 org 87,500.00 17,500.00

Jumlah 117,927.00

Dibulatkan 117,920.00

13 1 M¹ PASANG NOK GENTENG METAL

a Nok genteng metal 1.10 bh 60,000.00 66,000.00

b Paku payung 0.05 kg 17,500.00 875.00

c Pembantu tukang 0.25 org 50,000.00 12,500.00

Page 50: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 92,500.00

Dibulatkan 92,500.00

14 1 M

2 PASANG ATAP SENG GELOMBANG

a Seng gelombang 0.70 lbr 57,500.00 40,250.00

b Paku payung 0.02 kg 17,500.00 350.00

c Pembantu tukang 0.12 org 50,000.00 6,000.00

d Tukang kayu 0.06 org 87,500.00 5,250.00

Jumlah 51,850.00

Dibulatkan 51,850.00

15 1 M

2 PASANG NOK SENG UNTUK ATAP SENG GELOMBANG

a Seng plat BJLS 1.05 M1 33,300.00 34,965.00

b Paku payung 0.04 kg 17,500.00 700.00

c Pembantu tukang 0.15 org 50,000.00 7,500.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 49,290.00

Dibulatkan 49,290.00

16 1 M

2 PASANG ATAP POLYCARBONATE

a Polycarbonate 1.05 m

2 215,000.00 225,750.00

b Besi Hollow 1.50 btg 48,000.00 72,000.00

c Alat bantu 20 % harga material 1.00 ls 45,150.00 45,150.00

d Pembantu tukang 0.15 org 50,000.00 7,500.00

e Tukang kayu 0.05 org 87,500.00 4,375.00

Jumlah 354,775.00

Dibulatkan 354,770.00

17 1 M

2 PASANG ALUMINIUM FOIL

a Aluminium foil 1.05 m

2 5,500.00 5,775.00

b Alat bantu 20 % harga material 1.00 ls 1,155.00 1,155.00

c Pembantu tukang 0.15 org 50,000.00 7,500.00

d Tukang kayu 0.05 org 87,500.00 4,375.00

Page 51: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 18,805.00

Dibulatkan 18,800.00

XI PEKERJAAN PENUTUP PLAFON

1 1 M

2 PASANG RANGKA PLAFON ( UKRN 0,50 X 1,00 ) M, KAYU BORNEO SUPER

a Balok kayu borneo super 4 x 6 cm 0.01 m

3 5,400,000.00 64,800.00

b Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00

c Pembantu tukang 0.15 org 50,000.00 7,500.00

d Tukang kayu 0.25 org 87,500.00 21,875.00

Jumlah 95,925.00

Dibulatkan 95,900.00

2 1 M

2 PLAFON GRC ( 60 X 1,20 ) M, TEBAL 4 MM

a Pelat GRC tebal 4 mm 1.10 lbr 47,500.00 52,250.00

b Paku 1 cm 0.01 kg 17,500.00 175.00

c Pembantu tukang 0.03 org 50,000.00 1,500.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 60,050.00

Dibulatkan 60,050.00

3 1 M

2 PLAFON Asbes ( 1,00 x 1,00 ) m, tebal 5 mm

a Pelat asbes tebal 5 mm 1.10 lbr 13,500.00 14,850.00

b Paku 1 cm 0.01 kg 17,500.00 175.00

c Pembantu tukang 0.03 org 50,000.00 1,500.00

d Tukang kayu 0.07 org 87,500.00 6,125.00

Jumlah 22,650.00

Dibulatkan 22,650.00

4 1 M

2 PLAFON Akustik ( 60 x 120 ) cm

a Akustik 600 x 1200 x 15 mm 1.50 lbr 70,000.00 105,000.00

b Paku 2 - 5 cm 0.05 kg 17,500.00 875.00

Page 52: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Pembantu tukang 0.06 org 50,000.00 3,000.00

d Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 117,625.00

Dibulatkan 117,620.00

5 1 M

2 PLAFON AKUSTIK ( 60 X 120 ) CM + RANGKA ALLUMINIUM

a Profil Alluminium "T" 3.60 M¹ 32,000.00 115,200.00

b Kawat seng polos 0.15 kg 13,400.00 2,010.00

c Ramset / dina bolt 1.00 bh 2,800.00 2,800.00

d Akustik 600 x 1200 x 15 mm 1.50 lbr 70,000.00 105,000.00

e Pembantu tukang 0.15 org 50,000.00 7,500.00

f Tukang kayu 0.20 org 87,500.00 17,500.00

Jumlah 250,010.00

Dibulatkan 250,010.00

6 1 M¹ LIST PLAFON PROFIL KAYU

a Listp profil kayu 1.10 M¹ 6,800.00 7,480.00

b Paku 2 cm 0.01 kg 17,500.00 175.00

c Pembantu tukang 0.05 org 50,000.00 2,500.00

d Tukang kayu 0.05 org 87,500.00 4,375.00

Jumlah 14,530.00

Dibulatkan 14,530.00

7 1 M¹ LIST PLAFON KAYU 1/4

a List kayu 1/4 1.10 M¹ 1,900.00 2,090.00

b Paku 2 cm 0.01 kg 17,500.00 175.00

c Pembantu tukang 0.05 org 50,000.00 2,500.00

d Tukang kayu 0.05 org 87,500.00 4,375.00

Jumlah 9,140.00

Dibulatkan 9,140.00

8 1 M

2 PLAFON TRIPLEK 4 MM + RANGKA KAYU BORNEO SUPER

a Balok kayu borneo super 0.02 m

3 5,400,000.00 124,200.00

b Paku 1- 12 cm 0.06 kg 17,500.00 1,050.00

Page 53: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Triplek 120 cm x 240 cm x 0,4 cm 0.39 lbr 42,000.00 16,380.00

d Pembantu tukang 0.27 org 50,000.00 13,500.00

e Tukang kayu 0.40 org 87,500.00 35,000.00

Jumlah 190,130.00

Dibulatkan 190,130.00

9 1 M

2 PLAFON TEAKWOOD 4 MM + RANGKA KAYU BORNEO SUPER

a Balok kayu borneo super 0.02 m

3 5,400,000.00 124,200.00

b Paku 1 - 12 cm 0.06 kg 17,500.00 1,050.00

c Teakwood 120 cm x 240 cm x 0,4 cm 0.39 lbr 82,000.00 31,980.00

d Pembantu tukang 0.27 org 50,000.00 13,500.00

e Tukang kayu 0.40 org 87,500.00 35,000.00

Jumlah 205,730.00

Dibulatkan 205,730.00

10 1 M

2 Plafon PAPAN 10 CM, TEBAL 1 CM + RANGKA KAYU BORNEO SUPER

a Balok kayu borneo super 0.02 m

3 5,400,000.00 124,200.00

b Paku 2 - 12 cm 0.20 kg 17,500.00 3,500.00

c Papan kayu kamper 0.02 m

3 9,980,000.00 199,600.00

d Pembantu tukang 0.35 org 50,000.00 17,500.00

e Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 388,550.00

Dibulatkan 388,550.00

11 1 M

2 Plafon GYPSUM BOARD, TEBAL 9 MM + RANGKA BESI HOLLOW

a Hollow 4/4 Zincromate 0.42 btg 48,000.00 19,920.00

b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00

c Gypsum board ( 120 x 240 x 9 ) mm 0.36 lbr 86,000.00 31,304.00

d Paku sekrup 25.00 bh 600.00 15,000.00

e Ramset / dina bolt 4.00 bh 2,800.00 11,200.00

f Cotton plaster 0.07 bh 55,500.00 3,996.00

g Compoun 0.13 kg 30,000.00 3,750.00

h Pembantu tukang 0.10 org 50,000.00 5,000.00

Page 54: 166742630 Analisa Harga Satuan Pekerjaan Medan

i Tukang kayu 0.05 org 87,500.00 4,375.00

Jumlah 99,795.00

Dibulatkan 99,790.00

XII PEKERJAAN SANITAIR

1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK

a Kloset duduk / monoblok 1.00 bh 2,300,000.00 2,300,000.00

b Perlengkapan ( 10% hrg kloset ) 230,000.00 230,000.00

c Pembantu tukang 3.30 org 50,000.00 165,000.00

d Tukang batu 1.10 org 87,500.00 96,250.00

Jumlah 2,791,250.00

Dibulatkan 2,791,250.00

2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN

a Kloset jongkok porselen 1.00 bh 170,000.00 170,000.00

b Semen PC (abu-abu) 0.12 sak 54,000.00 6,480.00

c Pasir pasang 0.01 m

3 84,000.00 840.00

d Pembantu tukang 1.00 org 50,000.00 50,000.00

e Tukang batu 1.50 org 87,500.00 131,250.00

Jumlah 358,570.00

Dibulatkan 358,570.00

3 MEMASANG 1 BUAH URINOIR

a Urinoir 1.00 bh 380,000.00 380,000.00

b Perlengkapan ( 30% hrg urinoir ) 114,000.00 114,000.00

c Semen PC (abu-abu) 0.12 sak 54,000.00 6,480.00

d Pasir pasang 0.01 m

3 84,000.00 840.00

e Pembantu tukang 1.00 org 50,000.00 50,000.00

f Tukang batu 1.00 org 87,500.00 87,500.00

Jumlah 638,820.00

Dibulatkan 638,820.00

4 MEMASANG 1 BUAH WASTAFEL DINDING

Page 55: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Wastafel 1.00 bh 220,000.00 220,000.00

b Perlengkapan ( 12% hrg kloset ) 26,400.00 26,400.00

c Semen PC ( abu-abu ) 0.12 sak 54,000.00 6,480.00

d Pasir pasang 0.01 m

3 84,000.00 840.00

e Pembantu tukang 1.20 org 50,000.00 60,000.00

f Tukang batu 1.45 org 87,500.00 126,875.00

Jumlah 440,595.00

Dibulatkan 440,590.00

5 MEMASANG 1 BUAH WASTAFEL KAKI

a Wastafel 1.00 bh 255,000.00 255,000.00

b Perlengkapan ( 12% hrg kloset ) 30,600.00 30,600.00

c Semen PC ( abu-abu ) 0.12 sak 54,000.00 6,480.00

d Pasir pasang 0.01 m

3 84,000.00 840.00

e Pembantu tukang 1.20 org 50,000.00 60,000.00

f Tukang batu 1.45 org 87,500.00 126,875.00

Jumlah 479,795.00

Dibulatkan 479,790.00

6 MEMASANG 1 BH SHOWER DINDING

a Shower dinding 1.00 bh 132,000.00 132,000.00

b Pembantu tukang 0.01 org 50,000.00 500.00

c Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 141,250.00

Dibulatkan 141,250.00

7 MEMASANG BAK MANDI FIBERGLASS UKURAN SEDANG

a Bak fibreglass 1.00 bh 178,000.00 178,000.00

b Perlengkapan ( 20% hrg bak ) 32,040.00 32,040.00

c Pembantu tukang 1.80 org 50,000.00 90,000.00

d Tukang batu 2.70 org 87,500.00 236,250.00

Jumlah 536,290.00

Dibulatkan 536,290.00

Page 56: 166742630 Analisa Harga Satuan Pekerjaan Medan

8 MEMASANG BAK KONTROL PASANGAN BATU BATA UKURAN 30 X 30 CM, TINGGI 35 CM

a Batu bata 0.15 m

3 650.00 97.50

b Semen PC (abu-abu) 0.88 sak 54,000.00 47,520.00

c Pasir pasang 0.07 m

3 84,000.00 5,880.00

d Batu kerikil 0.07 m

3 157,900.00 11,053.00

e Besi beton 1.60 kg 15,100.00 24,160.00

f Pasir beton 0.06 m

3 92,000.00 5,520.00

g Pembantu tukang 3.20 org 50,000.00 160,000.00

h Tukang batu 1.02 org 87,500.00 89,250.00

Jumlah 343,480.50

Dibulatkan 343,480.00

9 MEMASANG KICHEN ZINK/BAK CUCI PIRING STAINLESS STEEL

a Bak cuci stainless steel 1.00 bh 191,500.00 191,500.00

b Water Drain + Asesories 1.00 Set 88,000.00 88,000.00

c Pembantu tukang 0.03 org 50,000.00 1,500.00

d Tukang batu 0.30 org 87,500.00 26,250.00

Jumlah 307,250.00

Dibulatkan 307,250.00

10 MEMASANG 1 BH KRAN DIAMETER 3/4 " ATAU 1/2 "

a Kran air 1.00 bh 56,000.00 56,000.00

b Perlengkapan ( 2% hrg kran ) 1.00 ls 1,120.00 1,120.00

c Pembantu tukang 0.01 org 50,000.00 500.00

d Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 66,370.00

Dibulatkan 66,370.00

11 MEMASANG 1 BH KRAN AIR ANGSA

a Kran air angsa 1.00 bh 157,500.00 157,500.00

b Perlengkapan ( 2% hrg kran ) 1.00 ls 3,150.00 3,150.00

c Pembantu tukang 0.01 org 50,000.00 500.00

d Tukang batu 0.10 org 87,500.00 8,750.00

Page 57: 166742630 Analisa Harga Satuan Pekerjaan Medan

Jumlah 169,900.00

Dibulatkan 169,900.00

12 MEMASANG 1 BH FLOOR DRAIN

a Floor drain 1.00 bh 62,000.00 62,000.00

b Pembantu tukang 0.01 org 50,000.00 500.00

c Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 71,250.00

Dibulatkan 71,250.00

13 MEMASANG 1 BH TEMPAT SABUN

a Tempat Sabun 1.00 bh 32,000.00 32,000.00

b Pembantu tukang 0.01 org 50,000.00 500.00

c Tukang batu 0.10 org 87,500.00 8,750.00

Jumlah 41,250.00

Dibulatkan 41,250.00

XIII PEKERJAAN PERPIPAAN DAN POMPA

1 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ½"

a Pipa galvanis dia 1/2" 1.10 M¹ 15,300.00 16,830.00

b Perlengkapan ( 30% harga pipa ) 4,590.00 4,590.00

c Pembantu tukang 0.05 org 50,000.00 2,700.00

d Tukang pipa 0.09 org 87,500.00 7,875.00

Jumlah 31,995.00

Dibulatkan 31,990.00

2 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ¾"

a Pipa galvanis 1.10 M¹ 20,850.00 22,935.00

b Perlengkapan ( 30% harga pipa ) 6,255.00 6,255.00

c Pembantu tukang 0.05 org 50,000.00 2,700.00

d Tukang pipa 0.09 org 87,500.00 7,875.00

Jumlah 39,765.00

Page 58: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 39,760.00

3 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1"

a Pipa galvanis 1.10 M¹ 30,500.00 33,550.00

b Perlengkapan ( 30% harga pipa ) 9,150.00 9,150.00

c Pembantu tukang 0.05 org 50,000.00 2,700.00

d Tukang pipa 0.09 org 87,500.00 7,875.00

Jumlah 53,275.00

Dibulatkan 53,270.00

4 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1½"

a Pipa galvanis 1.10 M¹ 34,750.00 38,225.00

b Perlengkapan ( 30% harga pipa ) 10,425.00 10,425.00

c Pembantu tukang 0.11 org 50,000.00 5,400.00

d Tukang pipa 0.18 org 87,500.00 15,750.00

Jumlah 69,800.00

Dibulatkan 69,800.00

5 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 3"

a Pipa PVC type D 1.10 M¹ 6,750.00 7,425.00

b Perlengkapan ( 30% harga pipa ) 2,025.00 2,025.00

c Pembantu tukang 0.10 org 50,000.00 5,000.00

d Tukang pipa 0.18 org 87,500.00 15,750.00

Jumlah 30,200.00

Dibulatkan 30,200.00

6 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 4"

a Pipa PVC type D 1.10 M¹ 9,000.00 9,900.00

b Perlengkapan ( 30% harga pipa ) 2,700.00 2,700.00

c Pembantu tukang 0.13 org 50,000.00 6,500.00

d Tukang pipa 0.22 org 87,500.00 19,250.00

Jumlah 38,350.00

Dibulatkan 38,350.00

7 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ½"

Page 59: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Pipa PVC 1.10 M¹ 5,750.00 6,325.00

b Perlengkapan ( 30% harga pipa ) 1,725.00 1,725.00

c Pembantu tukang 0.04 org 50,000.00 1,800.00

d Tukang pipa 0.06 org 87,500.00 5,250.00

Jumlah 15,100.00

Dibulatkan 15,100.00

8 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ¾"

a Pipa PVC 1.10 M¹ 7,700.00 8,470.00

b Perlengkapan ( 30% harga pipa ) 2,310.00 2,310.00

c Pembantu tukang 0.03 org 50,000.00 1,500.00

d Tukang pipa 0.06 org 87,500.00 5,250.00

Jumlah 17,530.00

Dibulatkan 17,530.00

9 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 1"

a Pipa PVC 1.10 M¹ 14,000.00 15,400.00

b Perlengkapan ( 30% harga pipa ) 4,200.00 4,200.00

c Pembantu tukang 0.04 org 50,000.00 1,800.00

d Tukang pipa 0.06 org 87,500.00 5,250.00

Jumlah 26,650.00

Dibulatkan 26,650.00

10 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 2"

a Pipa PVC 1.10 M¹ 24,000.00 26,400.00

b Perlengkapan ( 30% harga pipa ) 7,200.00 7,200.00

c Pembantu tukang 0.05 org 50,000.00 2,700.00

d Tukang pipa 0.09 org 87,500.00 7,875.00

Jumlah 44,175.00

Dibulatkan 44,170.00

11 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 4"

a Pipa PVC 1.10 M¹ 51,700.00 56,870.00

b Perlengkapan ( 30% harga pipa ) 15,510.00 15,510.00

Page 60: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Pembantu tukang 0.08 org 50,000.00 4,050.00

d Tukang pipa 0.14 org 87,500.00 11,812.50

Jumlah 88,242.50

Dibulatkan 88,240.00

12 MEMBUAT 1 BH SEPTICTANK PASANGAN BATU BATA DAN REMBESAN

a Galian tanah Septictank & rembesan 7.5 m

3 38,500.00 288,750.00

b Pasir urug 0.21 m

3 67,000.00 14,070.00

c Lantai kerja 2.25 m

3 648,800.00 1,459,800.00

d Pasang bata 1 Pc : 2 Psr 15.00 m

2 89,270.00 1,339,050.00

e Pelat beton penutup dan balok 0.30 m

3 5,711,800.00 1,713,540.00

f Pipa PVC 4 inci AW & perlengkapannya 5.40 M1 51,700.00 279,180.00

g Plesteran 1 Pc : 3 Psr 30.00 m

2 31,800.00 954,000.00

h Pasangan ijuk 5.00 IKAT 7,500.00 37,500.00

i Urugan kerikil 3,5 cm 1.05 m

3 112,400.00 118,020.00

j Pipa PVC 4 inci AW dilobang 9.00 M1 51,700.00 465,300.00

k Urugan kembali 1.13 m

3 11,000.00 12,430.00

l Pembantu tukang 4.00 org 50,000.00 200,000.00

m Tukang batu 3.00 org 87,500.00 262,500.00

Jumlah 7,144,140.00

Dibulatkan 7,144,140.00

13 MEMASANG 1 BH POMPA AIR

a Pompa Air 100 Watt 1.00 bh 800,000.00 800,000.00

b Perlengkapan ( 25% harga pompa ) 200,000.00 200,000.00

c Pembantu tukang 0.08 org 50,000.00 4,050.00

d Tukang Pipa 0.14 org 87,500.00 11,812.50

Jumlah 1,015,862.50

Dibulatkan 1,015,860.00

Page 61: 166742630 Analisa Harga Satuan Pekerjaan Medan

XIV PEKERJAAN PENUTUP BESI DAN BAJA

1 1 KG PASANG RANGKA ATAP BAJA

a Besi profil WF 1.10 kg 16,550.00 18,205.00

b Meni besi 0.08 kg 27,500.00 2,200.00

c Peralatan las ( 5 % material ) 1.00 ls 910.25 910.25

d Elektroda 0.20 ls 18,000.00 3,600.00

e Tukang besi 0.04 org 87,500.00 3,500.00

f Pembantu tukang 0.06 org 50,000.00 3,000.00

Jumlah 31,415.25

Dibulatkan 31,410.00

2 1 KG PASANG RANGKA ATAP BESI SIKU

a Besi Siku 1.10 kg 16,550.00 18,205.00

b Meni besi 0.10 kg 27,500.00 2,750.00

c Peralatan las ( 5 % material ) 1.00 ls 910.25 910.25

d Elektroda 0.15 ls 18,000.00 2,700.00

e Baud 0.20 kg 15,100.00 3,020.00

f Tukang besi 0.04 org 87,500.00 3,500.00

g Pembantu tukang 0.06 org 50,000.00 3,000.00

Jumlah 34,085.25

Dibulatkan 34,080.00

3 1 KG PASANG GORDING BESI C

a Besi C 1.10 kg 14,100.00 15,510.00

b Meni besi 0.10 kg 27,500.00 2,750.00

c Peralatan las ( 5 % material ) 1.00 ls 775.50 775.50

d Elektroda 0.15 ls 18,000.00 2,700.00

e Baud 0.20 kg 15,100.00 3,020.00

f Tukang besi 0.04 org 87,500.00 3,500.00

g Pembantu tukang 0.06 org 50,000.00 3,000.00

Jumlah 31,255.50

Dibulatkan 31,250.00

Page 62: 166742630 Analisa Harga Satuan Pekerjaan Medan

4 1 M

2 PASANG PINTU ROLLING DOOR BESI

a Rolling door besi 1.00 m

2 782,000.00 782,000.00

b Tukang besi 1.50 org 87,500.00 131,250.00

c Pembantu tukang 1.05 org 50,000.00 52,500.00

Jumlah 965,750.00

Dibulatkan 965,750.00

5 1 BH PASANG PINTU BESI UKURAN 0,8 X 2 M

a Pintu besi jadi 1.00 bh 400,000.00 400,000.00

b Tukang besi 1.05 org 87,500.00 91,875.00

c Pembantu tukang 1.05 org 50,000.00 52,500.00

Jumlah 544,375.00

Dibulatkan 544,370.00

6 1 M

2 PASANG TERALIS BESI

a Besi strip 2 mm x 3 cm 11.50 M¹ 14,100.00 162,150.00

b Tukang las 1.20 org 75,000.00 90,000.00

c Pembantu tukang 1.20 org 50,000.00 60,000.00

Jumlah 312,150.00

Dibulatkan 312,150.00

7 1 M

2 PASANG KAWAT HARMONIKA

a Kawat harmonika 1.10 m

2 18,000.00 19,800.00

b Paku 2 - 5 cm 0.02 kg 17,500.00 350.00

c Papan kayu kamper medan 0.00 m

3 6,750,000.00 12,150.00

d Pembantu tukang 0.10 org 50,000.00 5,000.00

e Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 46,050.00

Dibulatkan 46,050.00

8 1 M

1 PASANG TALANG DATAR, SENG PLAT BJLS

a Seng plat BJLS 1.00 M1 33,300.00 33,300.00

b Paku 2 - 5 cm 0.02 kg 17,500.00 262.50

c Papan kayu borneo super 0.01 m

3 5,660,000.00 54,336.00

Page 63: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Flincote / meni besi 0.25 kg 22,000.00 5,500.00

e Pembantu tukang 0.15 org 50,000.00 7,500.00

f Tukang kayu 0.40 org 87,500.00 35,000.00

Jumlah 135,898.50

Dibulatkan 135,890.00

9 1 M

1 PASANG TALANG MIRING, SENG PLAT BJLS

a Seng plat BJLS 0.50 M1 33,300.00 16,650.00

b Paku 2 - 5 cm 0.02 kg 17,500.00 262.50

c Papan kayu borneo super 0.02 m

3 5,660,000.00 107,540.00

d Flincote / meni besi 0.30 kg 22,000.00 6,600.00

e Pembantu tukang 0.04 org 50,000.00 2,000.00

f Tukang kayu 0.40 org 87,500.00 35,000.00

Jumlah 168,052.50

Dibulatkan 168,050.00

XV PEKERJAAN ALUMINIUM

1 1 M

2 PASANG PINTU ROLLING DOOR ALUMINIUM

a Rolling door aluminium 1.00 m

2 782,000.00 782,000.00

b Tukang besi konstruksi 1.50 org 87,500.00 131,250.00

c Pembantu tukang 1.05 org 50,000.00 52,500.00

Jumlah 965,750.00

Dibulatkan 965,750.00

2 1 M

2 PASANG PINTU ALUMINIUM PABRIKAN

a Pintu alluminium 1.00 bh 400,000.00 400,000.00

b Tukang batu 1.05 org 75,671.00 79,454.55

c Pembantu tukang 1.05 org 50,000.00 52,500.00

Jumlah 531,954.55

Dibulatkan 531,950.00

Page 64: 166742630 Analisa Harga Satuan Pekerjaan Medan

3 1 UNIT KUSEN JENDELA ALUMINIUM 2 LUBANG DGN 2 DAUN JENDELA (UKURAN 1,6 X 1,5 M)

a Profil aluminium 4" natural (+ spare 20 %) 9.24 M1 78,000.00 720,720.00

b Profil daun jendela alm.( + spare 20%) 11.04 M1 75,600.00 834,624.00

c Kaca polos 3 mm 2.40 m

2 90,000.00 216,000.00

d Engsel jendela 4.00 ps 22,000.00 88,000.00

e Grendel jendela 2.00 bh 19,500.00 39,000.00

f Kait angin 2.00 bh 19,800.00 39,600.00

g Acesories ( 6 % harga bahan) 1.00 ls 106,280.64 106,280.64

h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 144,144.00 144,144.00

i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 166,924.80 166,924.80

Jumlah 2,355,293.44

Dibulatkan 2,355,290.00

4

1 UNIT KUSEN JENDELA ALUMINIUM 3 LUBANG DGN 2 DAUN JENDELA DAN 1 KACA MATI (UKURAN 2 X

1,5 M)

a Profil aluminium 4" natural (+ spare 20 %) 12.00 M1 78,000.00 936,000.00

b Profil daun jendela alm.( + spare 20%) 11.04 M1 75,600.00 834,624.00

c Kaca polos 3 mm 3.00 m

2 90,000.00 270,000.00

d Engsel jendela 4.00 ps 22,000.00 88,000.00

e Grendel jendela 2.00 bh 19,500.00 39,000.00

f Kait angin 2.00 bh 19,800.00 39,600.00

g Acesories ( 6 % harga bahan ) 1.00 ls 122,437.44 122,437.44

h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 187,200.00 187,200.00

i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 166,924.80 166,924.80

Jumlah 2,329,661.44

Dibulatkan 2,329,660.00

5

1 UNIT KUSEN PINTU JENDELA GENDONG ALUMINIUM DGN 2 JNDL DAN 1 PNT TEAKWOOD (UKR 2,2 X

2,7 M)

a Profil aluminium 4" natural (+ spare 20 %) 17.04 M1 78,000.00 1,329,120.00

b Profil daun jendela alm.( + spare 20%) 14.88 M1 75,600.00 1,124,928.00

c Kaca polos 3 mm 3.96 m

2 90,000.00 356,400.00

Page 65: 166742630 Analisa Harga Satuan Pekerjaan Medan

d Daun pintu teakwood 1.80 m

2 432,600.00 778,680.00

e Engsel jendela 4.00 ps 22,000.00 88,000.00

f Grendel jendela 2.00 bh 19,500.00 39,000.00

g Kait angin 4.00 bh 19,800.00 79,200.00

h Engsel pintu 3.00 ps 25,000.00 75,000.00

i Grendel pintu 1.00 bh 33,000.00 33,000.00

j Kunci tanam 1.00 bh 22,000.00 22,000.00

k Acesories ( 6 % harga bahan ) 1.00 ls 140,522.40 140,522.40

l Upah pembuatan profil ( 20 % bahan ) 1.00 ls 17,600.00 17,600.00

m Upah pembuatan daun jendela (20 % bahan) 1.00 ls 7,800.00 7,800.00

Jumlah 4,091,250.40

Dibulatkan 4,091,250.00

6 1 UNIT KUSEN PINTU ALUMINIUM UKR 0.9 X 2,7 M

a Profil aluminium 4" natural (+ spare 20 %) 7.56 M1 78,000.00 589,680.00

b Kaca polos 3 mm untuk bovenlight 0.45 m

2 90,000.00 40,500.00

c Daun pintu tekwood 1.68 m

2 432,600.00 726,768.00

d Engsel pintu 3.00 ps 25,000.00 75,000.00

e Grendel pintu 1.00 bh 33,000.00 33,000.00

f Kunci tanam 1.00 bh 22,000.00 22,000.00

g Acesories ( 6 % ) 1.00 ls 37,810.80 37,810.80

h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 117,936.00 117,936.00

Jumlah 1,642,694.80

Dibulatkan 1,642,690.00

7 1 BH BOVENLIGHT ALMUNIUM DENGAN KISI-KISI ALMUNIUM PLAT (UKURAN 0,5 X 1 M)

a Profil Aluminium 4" natural + upah 20% 3.60 M1 90,000.00 324,000.00

b Plat Aluminium untuk Jalusi 5.00 M1 20,000.00 100,000.00

c Acesories ( 6 % ) 1.00 ls 19,440.00 19,440.00

d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 23,587.20 23,587.20

Jumlah 467,027.20

Dibulatkan 467,020.00

Page 66: 166742630 Analisa Harga Satuan Pekerjaan Medan

8 1 BH BOVENLIGHT ALMUNIUM UKURAN 0,5 X 1 M DENGAN BAGIAN DALAM KACA

a Profil Aluminium 4" natural + upah 20% 3.60 M1 78,000.00 280,800.00

b Kaca Polos 3 mm 0.50 m

2 90,000.00 45,000.00

c Acesories ( 6 % ) 1.00 ls 16,848.00 16,848.00

d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 4,717.44 4,717.44

Jumlah 347,365.44

Dibulatkan 347,360.00

XVI PEKERJAAN KACA & PENGGANTUNG

1 1 BUAH PASANG KUNCI TANAM BESAR

a Kunci tanam besar 1.00 bh 189,000.00 189,000.00

b Pembantu tukang 0.06 org 50,000.00 3,000.00

c Tukang kayu 0.60 org 87,500.00 52,500.00

Jumlah 244,500.00

Dibulatkan 244,500.00

2 1 BUAH PASANG KUNCI TANAM SEDANG

a Kunci tanam sedang 1.00 bh 55,000.00 55,000.00

b Pembantu tukang 0.01 org 50,000.00 500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 99,250.00

Dibulatkan 99,250.00

3 1 BUAH PASANG KUNCI BULAT PUTAR KAMAR MANDI

a Kunci bulat putar kamar mandi 1.00 bh 55,000.00 55,000.00

b Pembantu tukang 0.01 org 50,000.00 250.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 99,000.00

Page 67: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 99,000.00

4 1 BUAH PASANG ENGSEL PINTU

a Engsel pintu 1.00 bh 25,000.00 25,000.00

b Pembantu tukang 0.02 org 50,000.00 750.00

c Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 38,875.00

Dibulatkan 38,870.00

5 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU

a Engsel jendela 1.00 bh 22,000.00 22,000.00

b Pembantu tukang 0.01 org 50,000.00 500.00

c Tukang kayu 0.10 org 87,500.00 8,750.00

Jumlah 31,250.00

Dibulatkan 31,250.00

6 1 BUAH PASANG KAIT ANGIN

a Kait angin 1.00 bh 19,800.00 19,800.00

b Pembantu tukang 0.02 org 50,000.00 750.00

c Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 33,675.00

Dibulatkan 33,670.00

7 1 BUAH PASANG DOOR CLOSER

a Door closer 1.00 bh 380,000.00 380,000.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 426,250.00

Dibulatkan 426,250.00

8 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER

a Door holder 1.00 bh 50,000.00 50,000.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 96,250.00

Page 68: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 96,250.00

9 1 BUAH PASANG PENAHAN PINTU / DOOR STOPER

a Door stoper 1.00 bh 66,000.00 66,000.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 112,250.00

Dibulatkan 112,250.00

10 1 BUAH PASANG GRENDEL / SLOOT PINTU

a Grendel / sloot pintu 1.00 bh 33,000.00 33,000.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 79,250.00

Dibulatkan 79,250.00

11 1 BUAH PASANG GRENDEL / SLOOT JENDELA

a Grendel / sloot jendela 1.00 bh 19,500.00 19,500.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 65,750.00

Dibulatkan 65,750.00

12 1 BUAH PASANG TARIKAN JENDELA

a Tarikan jendela 1.00 bh 18,000.00 18,000.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang kayu 0.50 org 87,500.00 43,750.00

Jumlah 64,250.00

Dibulatkan 64,250.00

13 1 M

2 PASANG KACA POLOS, TEBAL 3 MM

a Kaca polos 1.10 m

2 90,000.00 99,000.00

b Pembantu tukang 0.02 org 50,000.00 750.00

c Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 112,875.00

Page 69: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 112,870.00

14 1 M

2 PASANG KACA POLOS, TEBAL 5 MM

a Kaca polos 1.10 m

2 150,000.00 165,000.00

b Pembantu tukang 0.02 org 50,000.00 750.00

c Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 178,875.00

Dibulatkan 178,870.00

15 1 M

2 PASANG KACA RAY BAND, TEBAL 5 MM

a Kaca 1.10 m

2 199,000.00 218,900.00

b Pembantu tukang 0.02 org 50,000.00 750.00

c Tukang kayu 0.15 org 87,500.00 13,125.00

Jumlah 232,775.00

Dibulatkan 232,770.00

XVII PEKERJAAN PENGECATAN

1 1 M

2 MENGIKIS / MENGEROK / MENGELUPAS PERMUKAAN CAT TEMBOK LAMA

a Soda api 0.05 kg 44,000.00 2,200.00

b Pembantu tukang 0.05 org 50,000.00 2,500.00

c Tukang cat 0.02 org 87,500.00 1,750.00

Jumlah 6,450.00

Dibulatkan 6,450.00

2 1 M

2 MENDEMPUL DAN MENGGOSOK KAYU

a Dempul jadi 0.10 kg 24,000.00 2,400.00

b Minyak cat 0.03 kg 19,300.00 579.00

c Ampelas kasar 0.30 lbr 2,500.00 750.00

d Pembantu tukang 0.04 org 50,000.00 2,000.00

e Tukang cat 0.05 org 87,500.00 4,375.00

Jumlah 10,104.00

Page 70: 166742630 Analisa Harga Satuan Pekerjaan Medan

Dibulatkan 10,100.00

3 1 M

2 PENGECATAN KAYU LAMA

a Cat meni 0.25 kg 27,500.00 6,875.00

b Plamir 0.15 kg 23,100.00 3,465.00

c Ampelas 1.00 lbr 2,500.00 2,500.00

d Cat dasar 0.15 kg 41,000.00 6,150.00

e Cat penutup kwalitas baik 0.60 kg 39,000.00 23,400.00

f Pembantu tukang 0.05 org 50,000.00 2,500.00

g Tukang cat 0.15 org 87,500.00 13,125.00

Jumlah 58,015.00

Dibulatkan 58,010.00

4 1 M

2 PENGECATAN KAYU BARU

a Cat meni 0.50 kg 27,500.00 13,750.00

b Plamir 0.15 kg 23,100.00 3,465.00

c Ampelas 1.00 lbr 2,500.00 2,500.00

d Cat dasar 0.15 kg 41,000.00 6,150.00

e Cat penutup kwalitas baik 0.35 kg 39,000.00 13,650.00

f Pembantu tukang 0.05 org 50,000.00 2,500.00

g Tukang cat 0.15 org 87,500.00 13,125.00

Jumlah 55,140.00

Dibulatkan 55,140.00

5 1 M

2 PENGECATAN KAYU DENGAN POLITUR

a Politur 0.15 Ltr 35,000.00 5,250.00

b Dempul jadi 0.25 kg 24,000.00 6,000.00

c Ampelas 2.00 lbr 2,500.00 5,000.00

d Pembantu tukang 0.05 org 50,000.00 2,500.00

e Tukang cat 0.15 org 87,500.00 13,125.00

Jumlah 31,875.00

Dibulatkan 31,870.00

6 1 M

2 PENGECATAN KAYU DENGAN MELAMIK

Page 71: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Melamik 0.15 Ltr 32,000.00 4,800.00

b Dempul jadi 0.25 kg 24,000.00 6,000.00

c Ampelas 2.00 lbr 2,500.00 5,000.00

d Pembantu tukang 0.05 org 50,000.00 2,500.00

e Tukang cat 0.15 org 87,500.00 13,125.00

Jumlah 31,425.00

Dibulatkan 31,420.00

7 1 M

2 PENGECATAN KAYU DENGAN CAT RESIDU/TER

a Residu atau ter 0.35 Ltr 6,800.00 2,380.00

b Pembantu tukang 0.15 org 50,000.00 7,500.00

c Tukang cat 0.02 org 87,500.00 1,750.00

Jumlah 11,630.00

Dibulatkan 11,630.00

8 1 M

2 PENGECATAN TEMBOK/Plafon BARU KWALITAS SEDANG

a Plamir 0.10 kg 25,000.00 2,500.00

b Rol cat 0.01 bh 27,000.00 270.00

c Cat penutup kwalitas sedang 0.45 kg 15,000.00 6,750.00

d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00

e Ampelas 0.50 lbr 2,500.00 1,250.00

f Pembantu tukang 0.06 org 50,000.00 3,000.00

g Tukang cat 0.20 org 87,500.00 17,500.00

Jumlah 32,020.00

Dibulatkan 32,020.00

9 1 M

2 PENGECATAN TEMBOK/Plafon BARU KWALITAS BAIK

a Plamir 0.10 kg 25,000.00 2,500.00

b Rol cat 0.01 bh 27,000.00 270.00

c Cat penutup kwalitas baik 0.50 kg 44,000.00 22,000.00

d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00

e Ampelas 0.50 lbr 2,500.00 1,250.00

f Pembantu tukang 0.06 org 50,000.00 3,000.00

Page 72: 166742630 Analisa Harga Satuan Pekerjaan Medan

g Tukang cat 0.20 org 87,500.00 17,500.00

Jumlah 47,270.00

Dibulatkan 47,270.00

10 1 M

2 PENGECATAN TEMBOK LAMA

a Cat penutup kwalitas baik 0.40 kg 28,000.00 11,200.00

b Rol cat 0.01 bh 27,000.00 270.00

c Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00

d Ampelas 0.50 lbr 2,500.00 1,250.00

e Pembantu tukang 0.06 org 50,000.00 3,000.00

f Tukang cat 0.20 org 87,500.00 17,500.00

Jumlah 33,970.00

Dibulatkan 33,970.00

11 1 M

2 PENGECATAN EXTERIOR

a Cat tembok 0.36 kg 75,000.00 27,000.00

b Plamir tembok 0.16 kg 25,000.00 4,000.00

c Rol cat 0.01 bh 27,000.00 270.00

d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00

e Ampelas 0.50 lbr 2,500.00 1,250.00

f Pembantu tukang 0.20 org 50,000.00 10,000.00

g Tukang cat 0.30 org 87,500.00 26,250.00

Jumlah 69,520.00

Dibulatkan 69,520.00

12 1 M

2 MEMASANG WALLPAPER

a Wallpaper 1.20 m

2 23,400.00 28,080.00

b Lem Perekat 0.20 kg 32,000.00 6,400.00

c Pembantu tukang 0.02 org 50,000.00 1,000.00

d Tukang cat 0.15 org 87,500.00 13,125.00

Jumlah 48,605.00

Dibulatkan 48,600.00

13 1 M

2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI

Page 73: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Meni besi 0.10 kg 27,500.00 2,750.00

b Kuas 0.01 bh 14,000.00 140.00

c Pembantu tukang 0.02 org 50,000.00 1,000.00

d Tukang cat 0.20 org 87,500.00 17,500.00

Jumlah 21,390.00

Dibulatkan 21,390.00

14 1 M

2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN CAT

a Meni besi 0.10 kg 27,500.00 2,750.00

b Cat besi 0.13 kg 38,500.00 5,005.00

c Kuas 0.01 bh 14,000.00 140.00

d Ampelas 0.50 lbr 2,500.00 1,250.00

e Perancah kayu 0.01 m

3 75,000.00 750.00

f Pembantu tukang 0.20 org 50,000.00 10,000.00

g Tukang cat 0.20 org 87,500.00 17,500.00

Jumlah 37,395.00

Dibulatkan 37,390.00

XVIII PEKERJAAN LISTRIK

1 PASANG 1 TITIK STOP KONTAK

a Stop kontak 1.00 bh 21,500.00 21,500.00

b Kabel listrik NYM 3 x 2,5 mm 0.25 rol 450,000.00 112,500.00

c Aksesoris ( 20 % material ) 1.00 ls 22,500.00 22,500.00

d Pembantu tukang 0.20 org 50,000.00 10,000.00

e Tukang listrik 0.60 org 87,500.00 52,500.00

Jumlah 219,000.00

Dibulatkan 219,000.00

2 PASANG 1 TITIK LAMPU

a Saklar 1.00 bh 21,500.00 21,500.00

b Kabel Listrik NYM 2 x 2,5 mm 0.25 rol 415,000.00 103,750.00

Page 74: 166742630 Analisa Harga Satuan Pekerjaan Medan

c Aksesoris ( 20 % material ) 1.00 ls 20,750.00 20,750.00

d Pembantu tukang 0.20 org 50,000.00 10,000.00

e Tukang listrik 0.60 org 87,500.00 52,500.00

Jumlah 208,500.00

Dibulatkan 208,500.00

3 PASANG 1 BUAH LAMPU SL

a Lampu SL 1.00 bh 55,500.00 55,500.00

b Aksesoris ( 1 % alat ) 1.00 ls 555.00 555.00

c Tukang listrik 0.10 org 87,500.00 8,750.00

Jumlah 64,805.00

Dibulatkan 64,800.00

4 PASANG 1 BUAH LAMPU TL

a Lampu TL 1.00 bh 55,500.00 55,500.00

b Aksesoris ( 1 % alat ) 1.00 ls 555.00 555.00

c Tukang listrik 0.12 org 87,500.00 10,500.00

Jumlah 66,555.00

Dibulatkan 66,550.00

5 PASANG 1 BUAH LAMPU BARET

a Lampu Baret 1.00 bh 92,000.00 92,000.00

b Aksesoris ( 1 % alat ) 1.00 ls 920.00 920.00

c Tukang listrik 0.15 org 87,500.00 13,125.00

Jumlah 106,045.00

Dibulatkan 106,040.00

6 PASANG 1 BUAH LAMPU PIJAR

a Lampu Pijar 1.00 bh 6,000.00 6,000.00

b Aksesoris ( 1 % alat ) 1.00 ls 60.00 60.00

c Tukang listrik 0.10 org 87,500.00 8,750.00

Jumlah 14,810.00

Dibulatkan 14,810.00

7 PASANG 1 BUAH LAMPU TAMAN

Page 75: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Lampu Taman 1.00 bh 175,000.00 175,000.00

b Aksesoris ( 1 % alat ) 1.00 ls 1,750.00 1,750.00

c Tukang listrik 0.35 org 87,500.00 30,625.00

Jumlah 207,375.00

Dibulatkan 207,370.00

8 PASANG 1 BUAH PANEL

a Panel Listrik standart untuk Rumah 1.00 bh 300,000.00 300,000.00

b Aksesoris ( 10 % alat ) 1.00 ls 30,000.00 30,000.00

c Tukang listrik 1.00 org 87,500.00 87,500.00

Jumlah 417,500.00

Dibulatkan 417,500.00

XIX PEKERJAAN WATERPROOFING

1 PASANG 1 M

2 WATERPROOFING MEMBRAN

a Material Primer 2.50 kg 2,450.00 6,125.00

b Waterproofing Membrane 1.10 m

2 75,000.00 82,500.00

c Pengetesan ( 10 % material ) 1.00 ls 8,250.00 8,250.00

d Pembantu tukang 0.20 org 50,000.00 10,000.00

e Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 159,375.00

Dibulatkan 159,370.00

2 PASANG 1 M

2 WATERPROOFING COATING

a Pre treatment / Cleaning ( 10 % material ) 1.00 m

2 4,400.00 4,400.00

b Bahan Waterproofing Coating 1.00 kg 44,000.00 44,000.00

c Kuas 3 " 0.25 bh 14,000.00 3,500.00

d Pembantu tukang 0.20 org 50,000.00 10,000.00

e Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 114,400.00

Dibulatkan 114,400.00

3 PASANG 1 M

2 FLOOR HARDERNER

Page 76: 166742630 Analisa Harga Satuan Pekerjaan Medan

a Material Natural non Metalic 1.10 kg 44,000.00 48,400.00

b Aksesoris ( 10 % alat ) 1.00 ls 484.00 484.00

c Pembantu tukang 0.20 org 50,000.00 10,000.00

d Tukang batu 0.60 org 87,500.00 52,500.00

Jumlah 111,384.00