1
PROGRAM : PENGEMBANGAN DESTINASI PARIWISATA KEGIATAN : PENGEMBANGAN SARANA DAN PRASARANA PARIWISATA PEKERJAAN : PEMBANGUNAN KONSTRUKSI KOLAM RENANG DAN TERAPI AIR PANAS LOKASI : KOMPL. HWB PINANG AWAN, KEC. PAUH DUO KAB. SOLOK SELATAN A. KOLAM RENANG I PEKERJAAN PENDAHULUAN 17,223,156.72 Rp II PEKERJAAN TANAH 11,116,435.18 Rp III PEKERJAAN BETON 756,697,846.94 Rp IV PEKERJAAN TRENCH PIPA 15,105,895.06 Rp V PEKERJAAN SALURAN LIMPASAN 16,757,385.23 Rp VI PEKERJAAN LANTAI SELASAR 24,341,739.44 Rp VII PEKERJAAN KERAMIK LANTAI DAN GRILL BETON 229,420,481.60 Rp VIII PEKERJAAN INSTALASI AIR BERSIH 21,066,367.57 Rp B. BANGUNAN UTAMA I PEKERJAAN PENDAHULUAN 4,858,621.32 Rp II PEKERJAAN PONDASI 30,618,789.91 Rp III PEKERJAAN BETON DAN STRUKTUR 156,502,385.38 Rp IV PEKERJAAN DINDING DAN KUZEN 143,352,765.74 Rp V PEKERJAAN KAP ATAP 106,052,234.24 Rp VI PEKERJAAN PLAFOND 89,303,781.13 Rp VII PEKERJAAN LANTAI 94,032,255.15 Rp VIII PEKERJAAN PINTU DAN JENDELA 36,537,197.48 Rp IX PEKERJAAN FINISHING 22,737,788.04 Rp X PEKERJAAN INSTALASI LISTRIK 10,615,000.00 Rp XI PEKERJAAN SANITAIR 15,886,978.58 Rp XII PEKERJAAN RABAT KELILING BANGUNAN 15,956,687.25 Rp A. JUMLAH BIAYA FISIK 1,818,183,791.94 Rp B. PPN 10% 181,818,379.19 Rp C. TOTAL JUMLAH ( A + B ) 2,000,002,171.14 Rp D. DIBULATKAN 2,000,000,000.00 TERBILANG : DUA MILYAR RUPIAH Batusangkar, 28 Juni 2013 Penawar CV. INDOMO RAJA SAKTI ttd Ir. FERRY ERIANDY Wakil Direktur R E K A P I T U L A S I NO. LINGKUP PEKERJAAN JUMLAH (Rp.) REKAP

Upload: mashuri-koto

Post on 17-Jan-2016

5 views

Category:

Documents


1 download

DESCRIPTION

BHR

TRANSCRIPT

Page 1: 04 Rekapitulasi

PROGRAM : PENGEMBANGAN DESTINASI PARIWISATA

KEGIATAN : PENGEMBANGAN SARANA DAN PRASARANA PARIWISATA

PEKERJAAN : PEMBANGUNAN KONSTRUKSI KOLAM RENANG DAN TERAPI AIR PANAS

LOKASI : KOMPL. HWB PINANG AWAN, KEC. PAUH DUO KAB. SOLOK SELATAN

A. KOLAM RENANG

I PEKERJAAN PENDAHULUAN 17,223,156.72Rp

II PEKERJAAN TANAH 11,116,435.18Rp

III PEKERJAAN BETON 756,697,846.94Rp

IV PEKERJAAN TRENCH PIPA 15,105,895.06Rp

V PEKERJAAN SALURAN LIMPASAN 16,757,385.23Rp

VI PEKERJAAN LANTAI SELASAR 24,341,739.44Rp

VII PEKERJAAN KERAMIK LANTAI DAN GRILL BETON 229,420,481.60Rp

VIII PEKERJAAN INSTALASI AIR BERSIH 21,066,367.57Rp

B. BANGUNAN UTAMA

I PEKERJAAN PENDAHULUAN 4,858,621.32Rp

II PEKERJAAN PONDASI 30,618,789.91Rp

III PEKERJAAN BETON DAN STRUKTUR 156,502,385.38Rp

IV PEKERJAAN DINDING DAN KUZEN 143,352,765.74Rp

V PEKERJAAN KAP ATAP 106,052,234.24Rp

VI PEKERJAAN PLAFOND 89,303,781.13Rp

VII PEKERJAAN LANTAI 94,032,255.15Rp

VIII PEKERJAAN PINTU DAN JENDELA 36,537,197.48Rp

IX PEKERJAAN FINISHING 22,737,788.04Rp

X PEKERJAAN INSTALASI LISTRIK 10,615,000.00Rp

XI PEKERJAAN SANITAIR 15,886,978.58Rp

XII PEKERJAAN RABAT KELILING BANGUNAN 15,956,687.25Rp

A. JUMLAH BIAYA FISIK 1,818,183,791.94Rp

B. PPN 10% 181,818,379.19Rp

C. TOTAL JUMLAH ( A + B ) 2,000,002,171.14Rp

D. DIBULATKAN 2,000,000,000.00

TERBILANG : DUA MILYAR RUPIAH

Batusangkar, 28 Juni 2013

Penawar

CV. INDOMO RAJA SAKTI

ttd

Ir. FERRY ERIANDY

Wakil Direktur

R E K A P I T U L A S I

NO. LINGKUP PEKERJAAN JUMLAH (Rp.)

REKAP